Search by
Dispute centers on whether a contractual indemnity covers a third-party claim settled by the plaintiff
Parties contest the interpretation and scope of an indemnity clause in a 2001 construction contract
Conflict over whether indemnity can apply to settlement of allegations not proven in court
Open questions remain about the cause of the underlying damages and the indemnitor’s role
Summary judgment deemed inappropriate due to unresolved factual and interpretive issues
Ambiguities in contract language preclude a conclusive determination without full trial evidence
Facts and background of the dispute
In Fluor Enterprises Inc v Leder Investments Ltd, 2025 ABKB 234, Fluor Enterprises Inc. (“Fluor”) brought a third-party claim against Leder Investments Ltd. (“Leder”) seeking indemnity for amounts paid in settlement of a lawsuit brought by the Government of Alberta (“GOA”). The GOA alleged that a road project constructed by Fluor in the early 2000s contained defects due to improper road base materials and construction. Fluor, in turn, alleged that these defects were attributable to Leder, a subcontractor under a 2001 agreement, and therefore claimed indemnity under that agreement’s terms.
The original contract between Fluor and Leder included an indemnity clause stating that Leder would indemnify Fluor against claims “arising out of or attributable to” Leder’s performance or non-performance of its subcontract obligations. Fluor claimed that the defects alleged by the GOA arose from Leder’s supply of base gravel that failed to meet specifications. Fluor settled the GOA action for $3 million and sought full reimbursement from Leder.
Leder opposed the third-party claim, asserting that Fluor had not proven that the defects were caused by Leder’s work. Leder argued that the indemnity provision did not apply where no finding of fault had been made, and that significant factual issues remained about the cause of the failure and the reasonableness of the settlement. Fluor applied for summary judgment on the indemnity claim.
Discussion of the policy terms and clauses at issue
The case turned largely on the interpretation of the indemnity provision in the 2001 subcontract. The clause stated that Leder would indemnify Fluor from and against:
“all claims, demands, losses, costs, damages, actions, suits or proceedings by third parties that are in any manner based upon, arising out of or attributable to the performance or non-performance by the Subcontractor of its obligations under this Agreement.”
Fluor argued that the clause was broad enough to cover liability arising from any issues linked to Leder’s work, even where the claim was settled and not adjudicated. Leder contended that the clause did not create liability in the absence of proven wrongdoing and that there was insufficient evidence that the GOA’s allegations were connected to Leder’s actions.
Judicial reasoning and outcome
Justice Hollins dismissed Fluor’s application for summary judgment, concluding that the case raised multiple factual and legal issues that required a full trial. The Court noted that there was no direct evidence establishing that the road base materials supplied by Leder were defective or caused the alleged damage. The expert evidence was insufficiently conclusive to support a finding on summary judgment.
The Court also held that interpretation of the indemnity clause—particularly whether it extended to settled claims where liability was not admitted—was not clear on its face. Because the clause did not expressly state that it applied to allegations or settlements regardless of proven fault, and because the facts underlying the third-party claim were contested, the judge found that its scope could not be resolved without trial evidence.
Additionally, the Court emphasized that Fluor bore the burden of showing that the $3 million settlement was reasonable and causally linked to Leder’s actions. Given the conflicting evidence on what caused the road failure, and whether any damages were in fact attributable to Leder’s gravel supply, those questions could not be resolved without cross-examination and detailed analysis of the underlying project and engineering issues.
Ultimately, the application was dismissed, with the judge holding that this was not a case suitable for summary determination due to the genuine issues requiring a full trial, both on the facts and the interpretation of the indemnity clause.
This judgment addressed only the summary judgment application. Fluor’s $3 million indemnity claim remains unresolved and is to be determined at trial.
Download documents
Applicant
Respondent
Court
Court of King's Bench of AlbertaCase Number
2301 07978Practice Area
Civil litigationAmount
Not specified/UnspecifiedWinner
RespondentTrial Start Date