• CASES

    Search by

Plante v. City of Contrecoeur

Executive Summary: Key Legal and Evidentiary Issues

  • The plaintiff claimed $40,000 in damages against the municipality for issuing a permit to install a pool within a servitude.

  • The municipality denied responsibility, arguing it committed no fault in analyzing or issuing the permit and in applying its regulations.

  • The court considered whether the municipality had a duty to verify the existence and scope of the servitude beyond the documents provided.

  • Evidence addressed the adequacy of the permit application, the municipality’s compliance with its own regulatory requirements, and the plaintiff’s knowledge of the servitude.

  • The municipality obtained all documents required by regulation and did not receive the servitude deed or updated certificate of localization from the plaintiff.

  • The court found no fault by the municipality and dismissed the plaintiff’s claim, awarding legal costs against the plaintiff.

 


 

Facts and outcome of the case

Background and facts

Yves Plante filed a claim against the Ville de Contrecoeur, seeking $40,000 in damages following the issuance of a construction permit for an in-ground pool. The permit allowed installation of the pool within the boundaries of a servitude in favor of Hydro-Québec and Télébec. The plaintiff alleged that the sale price of his property had to be reduced by $40,000 because of the pool’s encroachment into the servitude. The originating application was filed on June 14, 2023.

The municipality reviewed the plaintiff’s permit application, which included site plans and other documents, but did not receive the deed of servitude or an updated certificate of localization showing the servitude. The permit was issued on June 14, 2021, and signed by the plaintiff on June 18, 2021. The plaintiff acquired the property on June 25, 2021. The pool was installed after the permit was granted. During a subsequent sale process, a new certificate of localization issued on December 16, 2022, showed the pool encroaching on the servitude. The buyer required a reduction in the sale price, and the plaintiff sought to recover this loss from the municipality.

Legal issues and arguments

The central legal issue was whether the Ville de Contrecoeur was civilly liable for damages resulting from the issuance of the permit. The plaintiff argued that the municipality should have checked the land registry or visited the site to identify the servitude before issuing the permit. The municipality argued that it had complied with all regulatory requirements and that the responsibility to disclose servitudes and provide all relevant documents rested with the applicant.

Court’s analysis

The court reviewed the obligations of municipalities in the permitting process, noting that municipalities are required to act with reasonable diligence but are not insurers of their citizens. The municipality had obtained all documents required by regulation, including the project site plan, but had not received the deed of servitude or an updated certificate of localization. The court found that the municipality was not required to conduct independent investigations into servitudes not disclosed in the application. The court also found that the plaintiff had knowledge of the servitude at least by June 25, 2021, but did not update the municipality or the contractor.

Outcome

The court concluded that the municipality had not committed any fault in issuing the permit for the installation of the pool. The court ordered the plaintiff to pay the legal costs of the proceeding. No damages were awarded.

Yves Plante
Law Firm / Organization
Self Represented
Ville de Contrecoeur
Law Firm / Organization
Poupart & Poupart Avocats Inc.
Lawyer(s)

Armand Poupart Jr.

Court of Quebec
505-22-032149-231
Civil litigation
Not specified/Unspecified
Defendant
14 June 2023