Search by
Dispute over unpaid amounts and extras under a renovation contract for converting a car dealership into an orthodontic office
Determination of whether Dr. Melnik was personally a party to the renovation contract
Assessment of which claimed extras were allowable and in what amounts
Evaluation of counterclaims for business losses, rent, storage costs, and construction delays
Consideration of the reliability and credibility of conflicting witness testimony
Calculation and set-off of damages between the parties based on claims and counterclaims
Facts and outcome of the case
Background and parties
Cakwell Ergonomic Solutions Inc., a construction company led by Mr. Conrad Bewsky, entered into a contract to renovate leased premises for Dr. Andrew Melnik and his corporation, Dr. A.K. Melnik Inc. The premises, previously a car dealership, were to be converted into an orthodontic office. Jim Pattison Industries Ltd. was the landlord, named as a defendant because Cakwell filed a builder’s lien on the property, though the action against the landlord was stayed.
Nature of the dispute
The relationship between Mr. Bewsky and Dr. Melnik began as a friendship and prior positive business dealings. The renovation project, however, became contentious. Cakwell claimed it was owed $503,499 for work completed under the renovation contract, three written change orders, and 228 additional extras for which there were no written change orders. The claims included breach of contract, contractual quantum meruit, and restitutionary quantum meruit for unjust enrichment.
Dr. Melnik and his corporation denied owing any further amounts, arguing that the renovation was not substantially complete and that they had already paid over half a million dollars, which they believed reflected the value of the work done. They disputed the extras and counterclaimed for over $500,000 in business losses, rent, storage costs, credits, and lien bond costs, alleging delays in completion.
Key legal and evidentiary issues
The court was asked to determine whether Dr. Melnik was personally a party to the contract, which extras were allowable, the terms and extensions of completion, and the validity of the counterclaims. The case involved extensive factual disputes, particularly regarding the scope of work, the necessity and authorization of extras, and responsibility for delays. The court also had to assess the credibility and reliability of the main witnesses, Mr. Bewsky and Dr. Melnik, whose recollections and interpretations of events often conflicted.
Outcome and judgment
The court found in favor of Cakwell Ergonomic Solutions Inc. on its primary claim, awarding $150,000. However, the court also found merit in the counterclaim by Dr. Melnik and Dr. A.K. Melnik Inc., awarding them $49,886. The two amounts were set off against each other, resulting in a net judgment of $100,114 payable by Dr. Melnik and Dr. A.K. Melnik Inc. to Cakwell. There was no specific mention of costs awarded in the provided excerpt, and the action against the landlord was stayed pending the outcome between the other parties .
Download documents
Plaintiff
Defendant
Court
Supreme Court of British ColumbiaCase Number
S202714Practice Area
Construction lawAmount
Not specified/UnspecifiedWinner
Trial Start Date