Search by
The enforceability and scope of the full and final releases signed by the plaintiff regarding the water damage claim.
Applicability of the insurance policy’s one-year limitation period to different aspects of the plaintiff’s claims.
Distinction between claims arising from water damage and those related to alleged contractor negligence.
Adequacy of evidence establishing when the plaintiff discovered the alleged contractor-related damages.
Appropriateness of resolving only part of the plaintiff’s claims through summary judgment.
Determination of whether all issues should proceed together to trial for efficiency and fairness.
Background and facts of the case
This case arises from a water loss incident that occurred on February 16, 2021, at the residence of the plaintiff, Conrad St. Denis. Following the incident, Intact Insurance Company retained Onside Restoration to perform remedial work on the property. Onside completed some of the repairs, but the plaintiff later accepted a cash payout from Intact and hired Brian Wilson to complete additional work. The plaintiff, representing himself, initiated legal proceedings on June 6, 2023, alleging a range of damages. These included reimbursement for property damage, lost income, pain and suffering due to uninhabitable living conditions, and financial losses resulting from the need to secure additional mortgages. The plaintiff also claimed that the contractors, including Onside Restoration and Brian Wilson, caused further damage to his property and failed to complete the repairs, with specific allegations that Brian Wilson absconded with funds without finishing the job.
Discussion of policy terms and releases
Central to Intact Insurance’s defense was the assertion that the plaintiff’s claims were contractually barred by the terms of two full and final releases signed by the plaintiff. These releases specifically referenced damages arising from the water loss of February 16, 2021. The court examined the language of the releases and determined that they were limited in scope, applying only to damages directly resulting from the water incident on the specified date. Claims related to alleged contractor negligence or additional damage caused by Onside Restoration or Brian Wilson were not covered by the releases. The policy’s limitation clause was also scrutinized, which barred actions against the insurer unless commenced within one year of the loss or damage. However, the court found that not all aspects of the plaintiff’s claim were subject to this limitation, particularly those not seeking recovery under the insurance policy but instead seeking redress for alleged third-party contractor damage.
Key evidentiary findings
The court noted that the timeline regarding when the plaintiff became aware of the alleged contractor-related damages was unclear. The earliest documented complaint to Intact about Onside’s incomplete asbestos removal was on December 23, 2021. There was no evidence to suggest the plaintiff knew of these issues earlier, nor that he was aware as early as June 6, 2021.
Summary judgment motion and outcome
Intact Insurance sought summary judgment to dismiss the plaintiff’s claim, arguing that it was either contractually or statutorily barred. The court, however, found that while some aspects of the plaintiff’s claims were likely barred by the releases or limitation period, other claims—particularly those concerning alleged contractor negligence—were not. The court emphasized that partial summary judgment should be reserved for cases where issues can be clearly separated and resolved efficiently. In this instance, the court determined that the issues were too intertwined and that resolving only part of the case would not result in cost savings or efficiency. As a result, the court denied Intact Insurance’s motion for summary judgment, deciding that all issues should proceed together to trial.
Ruling and overall outcome
Justice I. Carter ruled that summary judgment was not appropriate in this case, as the claims against Intact Insurance could not be fully resolved at this stage. The motion was dismissed, and the matter will proceed to trial for a comprehensive determination of all issues. No specific monetary award or costs were ordered in favor of any party at this stage, as the case remains ongoing and unresolved on its merits.
Download documents
Plaintiff
Defendant
Court
Superior Court of Justice - OntarioCase Number
CV-23-92332Practice Area
Insurance lawAmount
Not specified/UnspecifiedWinner
Trial Start Date