Search by
Judicial review sought to set aside two loan authorization bylaws approved by the District of Summerland.
The petitioner alleged the District withheld or misrepresented financial information during the approval process for the bylaws.
The court considered whether the increased costs of an unrelated sewage treatment plant project were material to the bylaws at issue.
Admissibility of evidence not before the District Council was addressed, with exceptions applied due to the case’s circumstances.
The court determined the council’s decisions were legislative and not subject to a duty of procedural fairness.
No evidence supported allegations of bad faith or procedural unfairness by the District Council.
Facts and outcome of the case
Background and parties
In this case, the petitioner, Bradley H. Besler, appeared in person and challenged the validity of Loan Authorization Bylaws 2024-035 and 2024-036 adopted by The Corporation of the District of Summerland. The respondent was represented by S.S. Manhas and N.S.A. Falzon. The bylaws allowed the District to borrow up to $2,693,470 for upgrades to Victoria Road South and up to $3,365,080 for upgrades to Wharton Street, with repayment over no more than 25 years.
Events leading to the dispute
On November 5, 2024, the District Council gave first, second, and third readings to the bylaws and chose to seek elector approval through an alternative approval process. Notices were published on January 16 and 23, 2025, and the deadline for elector response forms was set for February 25, 2025. Approval would be obtained if fewer than 1,002 valid response forms were received. The Corporate Officer certified that 7.66% of voters submitted valid response forms for Bylaw 035 and 9.26% for Bylaw 036, both below the 10% threshold. The bylaws were adopted on March 4, 2025.
During this period, the District also addressed a separate project involving upgrades to a sewage treatment plant, including a new pump gallery. The petitioner asserted that the costs of this project, which were discussed at a public meeting on January 27, 2025, and reported in a local newspaper on January 29, 2025, were not disclosed to voters during the alternative approval process for the road upgrade bylaws.
Petitioner’s claims
The petitioner argued that the District acted unreasonably and with procedural unfairness by not informing voters about the increased costs of the sewage treatment plant project when seeking approval for the bylaws. He alleged that District staff intentionally withheld information and referenced past conduct by a staff member as evidence of bad faith. The petitioner did not allege non-compliance with the statutory procedures of the Community Charter.
The court’s analysis
The court found that the sewage treatment plant project was unrelated to the loan authorization bylaws for road upgrades. It determined there was no evidence that the increased costs of the sewage project were material to the bylaws or the District’s financial health. The court held that the statutory requirements for the alternative approval process were strictly followed and that there was no requirement in the Community Charter to inform voters of unrelated financial information. The court also concluded that the council’s decisions were legislative in nature and not subject to a duty of procedural fairness. Even if a duty of fairness applied, the court found it was not breached, as the information about the sewage project was publicly available before the deadline for elector response forms. The court gave no weight to the petitioner’s allegations of bad faith, finding no evidence of such conduct by the District Council.
Outcome
The court dismissed the petition. The Corporation of the District of Summerland was the successful party. No costs or damages were awarded at this stage, but the parties were given leave to address the issue of costs if necessary.
Download documents
Respondent
Petitioner
Court
Supreme Court of British ColumbiaCase Number
S50660Practice Area
Administrative lawAmount
Not specified/UnspecifiedWinner
RespondentTrial Start Date