Search by
Background and parties
Paul and Susan Catania owned a waterfront cottage property in McDougall, Ontario, and engaged Jamesway Custom Homes Ltd., a general contractor based in Magnetawan, Ontario, to complete interior finishing and substantial exterior landscaping works for their new cottage. Collin James, the president and sole officer, director, and shareholder of Jamesway, acted as the directing mind and was granted leave to represent the corporation at trial. The dispute arose from a suite of estimates that Jamesway treated as firm quotes: an interior estimate (approximately $380,484.56 including HST), a major landscaping estimate (approximately $1,084,800 including HST), and a later “additional” estimate for finishing items and extra work. The plaintiffs had previously contracted with Linwood Homes to erect the shell of the cottage, complete the exterior envelope, and perform major mechanicals and drywall, while Jamesway was to assume the interior finishing and landscaping once Linwood’s work reached a handover stage.
The project scope and estimates
The first estimate covered interior work such as trim, finishes, and other completion items. The second, central to the dispute, was the landscaping estimate. It contemplated extensive exterior works, including clearing trees and stumps, supplying and trucking large quantities of fill, shaping and compacting a tennis court area, grading around the cottage, and, crucially, supplying and transporting approximately 2,640 tonnes of armour stone. The armour stone was to be purchased, hauled to, and stored at a nearby rental site on neighbouring Vowels Farm lands, and later moved in smaller loads to the cottage site to complete rock features and retainers that were functionally connected to the tennis court and overall landscaping schedule. A third, later estimate in June 2023 related to additional landscaping, driveway work, and further interior and exterior tasks, some of which were never commenced.
Payment history and value of work performed
Over roughly a year of dealings from July 2022 to June 2023, the Catanias paid Jamesway a total of $1,405,633.75. This included approximately $92,175.93 for a dock installation that was not in dispute, $298,457.22 toward the interior estimate, and $1,015,001.30 toward the landscaping estimate. The parties agreed on most of the quantification issues regarding work done and materials supplied under the three estimates, with two disputed items: an interior trim package and a granite gravel driveway. The court found there was no admissible evidence to attribute value to the trim package, as no trim was ever delivered to the cottage and any preparatory work was unquantified and would, in any event, belong in the defendants’ abandoned counterclaim. Similarly, no sufficient evidence supported the claimed $20,000 value for the driveway item. Excluding these items, the court held that the plaintiffs had received work and materials worth $930,813.70, leaving a differential – overpayment relative to value received – of $474,819.97. No part of that differential was repaid.
The armour stone plan and the large deposit
The core of the case lay in the treatment of the armour stone. In September 2022, Jamesway issued the landscaping estimate with a draw schedule that required a 50 per cent deposit of $542,400. Contemporaneous texts and an email of 12 September 2022 from Mr. James set out what he called “phase 1” of the landscaping, which expressly included: setting up a rental area in a nearby farm field, purchasing the armour stone required for the job, transporting the stone to that rental area, unloading and storing it there, maintaining the road to allow heavy trucks to pass over winter, and beginning large-scale site preparation and fill operations. The email tied the first draw of $542,400 to “procur[ing] all the materials, equipment and truckers,” explicitly including the pre-purchase and staging of the armour stone, with later draws triggered by project start and completion. The plaintiffs accepted the landscaping estimate and paid the $542,400 deposit on 27 September 2022, borrowing against their line of credit for this purpose. Both plaintiffs testified, and the court accepted, that they understood this large advance as specifically required to pre-purchase and stage the armour stone so that the exterior, particularly the tennis court, could be completed by late spring or early summer 2023.
Project delays and shifting relationship dynamics
The project was complex. Linwood’s interior work ran late, delaying the point at which Jamesway could begin interior finishing; cabinet installation was also delayed, and there were logistical challenges with access, weather, and coordination among trades. The plaintiffs acknowledged Linwood’s delays and accepted that drywall and interior readiness came later than hoped, although by March 2023 Jamesway had access to begin interior tasks. Initially, the relationship remained cordial, and the plaintiffs paid invoices, including a May 30 “progress invoice” that was in substance an advance on work “coming down the pipe” rather than completed work. They made this payment on June 2, 2023, in part to ensure cash flow would not be raised as a reason for slow progress, then later directed that the amount be applied toward outstanding exterior work under the additional estimate. As the summer of 2023 approached and it became clear that Jamesway projected interior completion only by October at best, the plaintiffs grew increasingly concerned. They had planned to use the cottage and tennis court that summer and had arranged furniture deliveries for late June, relying on earlier assurances that a “full court press” of Jamesway’s crews would be applied to their project.
Discovery of the armour stone issue
The plaintiffs’ concerns crystallized around the armour stone. In early June, Mr. Catania texted a detailed set of questions, including specifically asking about whether armour stone would be put in. Mr. James responded to other issues but was silent on the stone. On June 9, Mr. Catania emailed to demand to know where the armour stone was, asked for a count, and requested to see a dealer invoice. Again, no forthright answer was provided. Around the same time, the plaintiffs texted twice asking for the name of the quarry. Mr. James did not respond with supplier details, later claiming he had become guarded as he sensed potential legal escalation. At a site meeting on June 12, 2023, the plaintiffs confronted Mr. James directly. According to both plaintiffs’ evidence, which the court preferred, Mr. James initially suggested the stone was at the quarry or that a deposit had been put down, but upon pointed questioning from Mrs. Catania, he ultimately admitted that no armour stone had been purchased at all. The plaintiffs immediately treated the matter as straightforward: they had advanced funds on the explicit understanding that the stone would be purchased and staged; it had not been done; they demanded their money back and told Mr. James to cease work. Cameras were later installed, and the relationship ended.
Contractual analysis and fundamental breach
The court held that a binding landscaping contract was formed on 27 September 2022 when the plaintiffs accepted the landscaping estimate by paying the 50 per cent deposit. The contract encompassed the items listed in the landscaping estimate, including the purchase, transport, unloading, and storage of armour stone at the rental yard, and had as its core commercial purpose the timely completion of the exterior so the plaintiffs could enjoy their property – particularly the tennis court – by summer 2023. Although there was no explicit calendar date in the estimate itself, the court found on the evidence that there was a contemplated timeframe: the stone was to be purchased and stored in the fall or early winter after the deposit, and phase 1 landscaping was to be completed by late spring or early summer 2023. The judge applied the doctrine of fundamental breach, using established tests focusing on the ratio of unperformed obligations, seriousness to the innocent party, likely repetition, consequences, and the relationship of the unperformed part to the contract as a whole. In this case, the defendants entirely failed to perform the key obligation to purchase and stage the armour stone using the deposit, despite having represented that this was precisely why the substantial advance was needed. This failure was serious: it destroyed the plaintiffs’ trust, undermined the schedule for using their tennis court and exterior amenities, and left them servicing debt they had taken on solely to meet the contractor’s demands. The court rejected Mr. James’s explanations about quarry sufficiency, road conditions, access constraints, and sequencing as inconsistent with the contemporaneous documentary record and his own prior discovery evidence, and found nothing prevented him from ordering and staging the stone as promised. The judge concluded that the defendants’ failure deprived the homeowners of substantially the whole benefit of the landscaping contract and constituted a fundamental breach entitling them to terminate and claim damages.
Trust, breach of trust, and personal liability
Beyond contract, the court characterized the initial $542,400 landscaping deposit as subject to a Quistclose-type trust. The funds were advanced for a clearly defined, narrow purpose – acquiring and staging armour stone and related materials and logistics – and the plaintiffs did not authorize their use for any other purpose. While some portion of the landscaping payments may have been applied to other legitimate works, the net overpayment of $474,819.97 represented funds that, on the evidence, were not applied to provide corresponding value to the plaintiffs. The defendants provided no coherent accounting for how those funds were used, and Mr. James gave inconsistent evidence on whether the money remained in the corporate account or was used, for example, to purchase a tractor-trailer intended, but never actually used, for the project. The court held that the failure to use the funds for their specified purpose, and the failure to account, amounted to a breach of trust. As the directing mind of a closely held corporation who requested the deposit, decided not to purchase the stone, and deliberately avoided disclosing that fact, Mr. James was found to have knowingly participated in the breach of trust. Applying constructive trust principles, the court held him personally liable, jointly and severally with Jamesway, for the resulting loss.
Duty of honest contractual performance
The court also examined the common law duty of honest performance in contracts. While there was no explicit lie about a completed purchase order, the judge found a sustained, material concealment of the true state of affairs. Mr. James knew that no armour stone had been bought, yet he did not correct the plaintiffs’ reasonable assumption – created by his own representations – that the stone had been pre-purchased and staged for spring deployment. Even when directly questioned about the stone and the quarry in the days leading up to June 12, he said nothing to dispel the misapprehension. The court held this pattern of silence and evasion, directly tied to the performance of contractual obligations, to be a breach of the duty of honest performance. This breach further justified the plaintiffs’ decision to terminate the contract and seek damages.
Consumer protection law overlay
As an additional, independent basis, the court applied Ontario’s Consumer Protection Act, treating the landscaping agreement as a “future performance agreement” because payment in full and performance were not contemporaneous with contract formation. Under s. 26(2), where no specific commencement date is specified, a consumer may cancel if the supplier does not begin performance within 30 days of the agreement. Here, the court found that within 30 days of contract formation on September 27, 2022, the defendants had not begun performance of the armour-stone-related obligations: there was no order, no deposit to a supplier, and no delivery or staging at the rental site. That ongoing non-performance gave the plaintiffs a statutory right to cancel and recover their money, even if the court’s contract and trust analyses had been wrong. The defendants’ argument that the Consumer Protection Act could not be relied on because it was not pleaded was rejected; the judge accepted submissions that, both procedurally and under existing case law, the statute could still be invoked and that the defendants were not prejudiced or taken by surprise.
Damages, interest, and outcome
The court calculated damages by comparing the total paid by the plaintiffs to the value of work and materials actually received. After resolving the two disputed items against the defendants, the total value conferred was fixed at $930,813.70, against payments of $1,405,633.75, yielding an overpayment of $474,819.97. This amount was awarded as damages flowing from fundamental breach, breach of trust, and breach of the duty of honest performance. Recognizing that the cause of action arose when the defendants failed in the fall or early winter of 2022 to purchase, deliver, and store the armour stone, the judge ordered prejudgment interest on the $474,819.97 from January 1, 2023, to the date of judgment under the Courts of Justice Act. While the plaintiffs were held presumptively entitled to their costs, the quantum of costs was not fixed; the court instead directed a short timetable for written costs submissions, meaning the precise costs figure could not yet be determined from the reasons alone. In the result, judgment was granted in favour of the plaintiffs, Paul and Susan Catania, against both Jamesway Custom Homes Ltd. and Collin James, jointly and severally, for $474,819.97 in damages plus prejudgment interest from January 1, 2023, with the ultimate amount of costs to be determined later, such that the total monetary outcome in their favour is at least $474,819.97 plus interest, with the costs award not yet quantified.
Download documents
Plaintiff
Defendant
Court
Superior Court of Justice - OntarioCase Number
CV-23-00001336-0000Practice Area
Construction lawAmount
$ 474,819Winner
PlaintiffTrial Start Date