Search by
Facts of the case
CNOOC Petroleum North America ULC owned the K1A corridor pipelines at its Long Lake facility near Fort McMurray, Alberta. On July 15, 2015, the produced emulsion (PE) pipeline failed, resulting in a loss of containment. CNOOC sued Sunstone Projects Ltd. and Wood Group Canada, Inc. (together, Wood Group), which provided engineering services, and ITP SA, which supplied the pipe-in-pipe system. Its claim alleges that deficiencies in the design, engineering, manufacture and construction caused the failure and that both the PE pipeline and the BFW pipeline were unfit for service. Third parties named at various stages included Surerus Pipeline Inc., Stresstech Engineering Inc. and Thurber Engineering Ltd.
After an earlier adjournment from September 2025, trial was set for October 13, 2026, with 100 trial days allocated. Nine decisions issued in 2026 dealt with costs, discovery, the sequencing of expert reports, the reading-in of employee evidence and, once trial had begun, the qualification of one of CNOOC’s experts.
Policy and legislative provisions at issue
CNOOC’s Statement of Claim alleges that the pipelines are not fit for service, do not meet design specifications or applicable codes and standards, and “must be significantly repaired or replaced.” It estimates repair or replacement costs at at least $405,000,000 and claims damages of at least $450 million.
Several Alberta Rules of Court governed the applications. Rule 5.35 requires expert reports to be served in sequence: the party bearing the primary onus serves first, the opposing party serves rebuttal reports that may raise new issues, and the initial party may serve a surrebuttal that “responds only to the new issues raised in the rebuttal report.” Under Rule 8.16, no more than one expert may give opinion evidence on any one subject for a party unless the court permits otherwise. Rule 5.36 bars objections to an expert report at trial unless reasonable notice was given or the court permits the objection. Rule 5.29 allows a corporate witness’s questioning evidence to be read in at trial once a corporate representative acknowledges it as information of the corporation, and the representative cannot refuse merely because they disbelieve or disagree with it. Rules 5.17 and 5.30 govern who may be questioned and questioning on undertaking responses. Costs were governed by Rule 10.29(1), under which a successful party is generally entitled to costs, subject to the court’s discretion under Rules 10.31 and 10.33.
Expert admissibility at trial turned on the test from R v Mohan and White Burgess Langille Inman v Abbott and Haliburton Co. That test requires relevance, necessity, the absence of an exclusionary rule and a properly qualified expert, followed by a discretionary weighing of benefits against risks.
Reasoning and analysis
Early in 2026, the case management justice resolved several discovery and costs disputes. On costs from an earlier privilege application, Wood Group was refused the costs of cross-examining Marianne “Chuck” Davies, CNOOC’s former general counsel. Although the court rejected CNOOC’s res judicata argument, it took into account that those costs had already been sought and denied in related judicial review proceedings, and it treated the outcome as mixed success. Wood Group was then permitted to question Dean Kovacs, the former chief inspector of CNOOC’s Canadian gas operation, after the close of primary questioning. CNOOC had amended Undertaking Response 708 to assert an unwritten Pipeline Integrity Maintenance System (PIMS), relying solely on information from Mr. Kovacs. Because nothing before that amendment indicated that he had specific knowledge of the PIMS issue, questioning was allowed but confined to the amended response.
On refused undertakings arising from the questioning of corporate representative Sean Noe, the court ordered CNOOC to answer several requests. These included who selected the contractors for the replacement pipeline work and on what criteria, and how CNOOC identified the procedures it reported to the Alberta Energy Regulator. Other compelled requests concerned the award of front-end engineering design work to CNOOC Research Institute and the decision to retain COOEC Canada, which received a sole-source contract. Both entities sat within a corporate group under the common control of China Ocean Oil Group Co., Ltd., so the transactions were not at arm’s length. The court found the potential for conflicts of interest relevant to the reasonableness of CNOOC’s mitigation. A request requiring inquiries of an arm’s-length third party, China Petroleum Pipeline Engineering Company, Ltd., was properly refused, as were portions of other requests found overly broad or not relevant. Separately, Wood Group was awarded the costs of its earlier adjournment application at Column 5 of Schedule C on a multiple of four. Although it had unsuccessfully sought an adjournment sine die, the court found it substantively successful because CNOOC’s proposed January 2026 trial date was not workable.
In August 2026, the case management justice refused Wood Group’s application to strike Mr. Lamberson’s rebuttal report. Read together with ITP’s expert report by Mike Hylton, which raised Wood Group’s standard of care, the Lamberson report was proper rebuttal and did not duplicate CNOOC’s other experts contrary to Rule 8.16. CNOOC’s cross-application to strike Wood Group’s rebuttal reports also failed. The court extended the surrebuttal deadline to September 21, 2026, and left broader Mohan admissibility questions to be addressed at trial.
After surrebuttal reports were exchanged, Wood Group and ITP challenged four of them. The trial judge agreed that CNOOC bore the primary burden of proving that the pipelines were unfit and required repair or replacement. Even so, the primary reports of J. Phil Kormann, Jaspreet Hothi, James Oswell and David Weisgerber raised systemic deficiencies, so CNOOC had not split its case. The Weisgerber, Hothi and Carlson surrebuttals responded to new issues raised by Dr. Angelique Lasseigne, Michael Dowhopoluk and Greg Bridgewater. Dr. Williams’s report properly answered Mr. Dowhopoluk’s opinion that local remediation options would have been available, but it then advanced affirmative opinions that both pipelines would effectively need replacement. Sections 2.3, 2.4 and 2.5 of his report, along with the final sentence of the conclusion in section 2.6, were struck, limiting his evidence to sections 2.1 and 2.2. An adjournment was rejected as prejudicial to all parties.
The same judge ordered Wood Group’s corporate representative to acknowledge disputed employee evidence under Rule 5.29. That evidence included statements that Sunstone was the engineer of record, answers qualified with words such as “probably” or “I would imagine,” and a description of a quality assurance or quality control role. Rule 5.29 primarily concerns attribution, not admissibility. Acknowledgment is not a binding admission, and Wood Group remains free to contradict the evidence at trial.
Once trial had begun, CNOOC moved to strike Wood Group’s October 28, 2026 Notice of Objection to Mr. Lamberson’s evidence. The court found the notice reasonable. At the August 14, 2026 hearing, Wood Group’s counsel had said it would challenge Mr. Lamberson’s qualifications if his evidence proceeded. His reports were, at best, ambiguous about his qualifications until his September 21 surrebuttal report, in which he described himself as “not a practicing engineer,” established clearly for the first time that he was not an engineer. When the notice was served, he was scheduled to testify in February 2027, and CNOOC later chose to call him earlier. In the alternative, the court would have permitted the objection under Rule 5.36(2)(b).
On the qualification voir dire, the court found that Mr. Lamberson’s reports extended materially beyond project and construction management. They reached conclusions about what Sunstone, assumed to be Engineer of Record, was professionally or technically required to design, analyze, approve, provide or ensure. Mr. Lamberson has no engineering degree, has never been licensed or worked as an engineer, and has never worked on a project in Alberta or elsewhere in Canada. His CV and rebuttal report described a Bachelor of Science in Industrial Engineering and Technology from East Central University in Oklahoma, but his actual degree was in Industrial Education and Technology. Lack of Canadian experience was not disqualifying on its own. It mattered here because several opinions concerned the Engineer of Record’s responsibilities on an Alberta project, and his inability to show familiarity with material aspects of the regulatory framework reinforced the mismatch. Drawing on Brough v Yipp and Dulong v Merrill Lynch Canada Inc., the court held that substantial experience in an adjacent field does not, without more, establish expertise in another discipline. It distinguished a decision in which a power engineer had given operational opinions. Engineering premises ran through both reports, so selective redaction or a narrower qualification was not practicable.
In the alternative, the court would have excluded the evidence at the gatekeeping stage. The inaccurate degree description, his website’s attribution of engineering and technical expertise to him, and his evidence that the site had not been updated in five or six years all weighed against him. That last point was difficult to reconcile with the website’s disclosure of his June 2024 retainer by CNOOC. Taken together, these matters gave the court material concerns about his candour. A judge-alone trial reduced, but did not eliminate, the risks of admitting his evidence.
Ruling and overall outcome
In the most recent decision, Mr. Lamberson was not qualified as an expert and his rebuttal and surrebuttal reports were excluded in their entirety, a result in favour of Sunstone Projects Ltd. and Wood Group Canada, Inc. That decision orders no monetary relief and makes no costs order. Across the series, Wood Group received costs of the adjournment application at Column 5 of Schedule C on a multiple of four, and CNOOC received its costs of the Rule 5.29 application. Neither award was quantified, so no exact dollar amount can be determined. Each party bore its own costs on the August 2026 expert-report applications and on the surrebuttal application, the latter expressly as a matter of mixed success. Wood Group received no costs for the Davies cross-examination. Costs of the Kovacs and undertakings applications were left for the parties to agree or speak to. CNOOC’s underlying damages claim remains to be decided at trial.
Download documents
Plaintiff
Defendant
Other
Court
Court of King's Bench of AlbertaCase Number
1701 07427Practice Area
Corporate & commercial lawAmount
Not specified/UnspecifiedWinner
DefendantTrial Start Date