Search by
Background and factual context
Maplequest (Vaughan) Developments Inc. and Primont Homes (Vaughan) Inc. are opposing parties in a civil action in the Ontario Superior Court of Justice. The underlying dispute arose in a commercial context between two real estate developers, but the decision at issue is almost entirely concerned with procedure rather than the substantive merits of their business dispute. For approximately five years, Associate Justice Josefo case-managed the action and oversaw the parties’ progress through interlocutory steps. Over that period, he issued a series of orders directed at Maplequest requiring production and disclosure of documents and the payment of costs.
The record before the Divisional Court shows that Maplequest failed to comply with at least seven such orders relating to production and disclosure. Some of these were consent orders. A critical point came on May 26, 2025, when the associate judge issued a “last chance” peremptory order. That order required Maplequest to pay outstanding costs and to produce specified documents by June 13, 2025. Maplequest paid the costs, but by the time Primont’s motion to strike was heard, it had still not produced the required documents. The parties agreed that the outstanding production obligations related to documents relevant to Maplequest’s counterclaim.
The motion to strike before the associate judge
Primont moved under rules 30.08(2) and 60.12 of the Ontario Rules of Civil Procedure to strike Maplequest’s defence and counterclaim for persistent non-compliance with court orders. The motion came on for hearing on July 25, 2025. Maplequest had not served a factum and sought an adjournment, explaining that counsel had “other pressing deadlines.” The associate judge refused the adjournment and required counsel to argue the motion, noting that counsel nonetheless made able submissions.
On the motion, Maplequest did not argue in the alternative that, if any pleading was to be struck, it should be only the counterclaim. Instead, it resisted the striking remedy as a whole. After reviewing the lengthy procedural history, the associate judge found that Maplequest had engaged in a years-long pattern of delay and disregard for its disclosure obligations. He identified continuing defaults in respect of two significant production orders, emphasized that some delays appeared deliberately engineered, and concluded that Maplequest had treated court orders as “paper tigers” to be followed only when convenient. He further characterized Maplequest’s conduct as involving “prevarications,” “defiance,” and “unequivocal” non-compliance, with no satisfactory or credible explanation.
In his reasons, Associate Justice Josefo referred to and relied on the Court of Appeal’s decisions in Falcon Lumber Limited v. 2480375 Ontario Inc. (GN Mouldings and Doors), Advanced Farm Technologies-JA v. Yung Soon Farm Inc., and Rimon v. CBC Dragon Inc. Those cases articulate the principles governing the striking of a pleading for failure to comply with production obligations, including factors such as whether non-compliance is deliberate, whether defaults are cured, the materiality of the breach, and the impact on the opposing party and on the administration of justice. Applying those principles, and emphasizing Maplequest’s ongoing breach of his peremptory “last-chance” order, the associate judge concluded that lesser measures had failed and that the only remaining appropriate remedy was the “nuclear option” of striking Maplequest’s entire pleading, both defence and counterclaim.
The appeal and the applicable standard of review
Maplequest appealed to the Divisional Court, challenging the associate judge’s discretionary order. It accepted that the applicable standard of review was the appellate standard set out in Housen v. Nikolaisen: questions of mixed fact and law (which characterize this appeal) are reviewed only for palpable and overriding error. The Court also relied on Falcon Lumber, which instructs that an appellate court should defer to a motion judge’s discretionary case-management decision unless the judge applied the wrong legal principle or made a clear error in appreciating the evidence.
On appeal, Maplequest advanced a more targeted proportionality argument. It acknowledged its history of non-compliance but contended that, by the time of the motion, the only remaining breach related to production of documents relevant to the counterclaim. On that basis, it argued that the appropriate and proportionate remedy would have been to strike only the counterclaim, while preserving the statement of defence. Maplequest also argued that the associate judge erred by not expressly working through each Falcon Lumber factor in a structured, itemized way, and by giving insufficient weight to the policy of deciding cases on their merits. It relied on Koohestani v. Mahmood, where the Court of Appeal set aside an order striking a defence in part because the motion judge did not properly weigh the strength of the defence and the peripheral nature of the default.
Primont, in response, submitted that Maplequest was effectively raising a new argument on appeal: the suggestion that only the counterclaim should be struck had never been put to the associate judge. Primont maintained that the associate judge had clearly considered the governing principles, including the Falcon Lumber factors and later cases like Advanced Farm and Rimon, and that his factual findings about Maplequest’s pattern of delay and defiance were fully supported by the record. On this basis, Primont argued there was no basis for appellate intervention.
The Divisional Court’s analysis of the striking order
Justice Brownstone held that the associate judge’s decision attracted significant deference. The Court endorsed the description of striking-out powers as an “essential management tool” for case-management judges who are repeatedly exposed to the same file and are best placed to assess whether a party is deliberately stalling, acting in bad faith, or abusing the court’s process. Within this framework, the Court reviewed the associate judge’s reasoning and found that, even though he did not list each Falcon Lumber factor under separate headings, he substantively addressed all of the key considerations.
Justice Brownstone noted that the associate judge had clearly found Maplequest’s breaches to be deliberate and unequivocal, unsupported by any reasonable explanation, and still ongoing at the time of the motion. He further accepted the associate judge’s conclusion that Maplequest’s conduct had caused increased costs and delay for Primont, and had undermined the court’s ability to do justice in the case. The fact that the associate judge’s reasons were not organized as a checklist did not amount to legal error; what mattered was that the correct principles were applied in substance.
On the merits-based arguments, the Divisional Court observed that, in the context of failures to comply with disclosure and production obligations, the case law assigns only a limited role to the underlying strength of a party’s claim or defence. The court emphasized that one would reasonably expect a party with a strong case to comply promptly with procedural obligations, which Maplequest had not done. As a result, the omission of a detailed discussion of the merits of the defence did not undercut the validity of the associate judge’s analysis.
The proportionate remedy and the new argument about striking only the counterclaim
A central appellate issue was whether proportionality required striking only Maplequest’s counterclaim, since the outstanding breach related to counterclaim-specific documents. Maplequest argued that, because the affidavit evidence on the motion made that link clear, the associate judge should have considered striking only the counterclaim as part of his proportionality analysis, even though Maplequest had not asked him to do so.
Justice Brownstone recognized that appellate courts can sometimes entertain new arguments where the factual record is complete and the issue is tightly connected to what was before the first-instance judge. Exercising that discretion, the Court chose to consider Maplequest’s proportionality argument on its merits. However, the Court ultimately rejected it. It stressed that the associate judge considered Maplequest’s entire litigation history, not just the final outstanding breach, and concluded that all lesser tools—case conferences, repeated encouragement, multiple orders, and stepped remedies—had failed to secure Maplequest’s consistent compliance.
The Court held that the associate judge was not required to compartmentalize Maplequest’s misconduct into “defence-related” and “counterclaim-related” behaviour, especially when the argument for that distinction had not been advanced before him. Given the pattern of “deliberately engineered” delays and continuing non-compliance with a clearly identified last-chance order, it was open to the associate judge to find that striking both the defence and counterclaim was the only sanction with sufficient weight to vindicate the integrity of the court’s process. There was no palpable and overriding error in his conclusion that this “nuclear option” was proportionate in the circumstances.
The request to file a new statement of defence
In the alternative, Maplequest asked the Divisional Court to permit it to file a new statement of defence, even if the associate judge’s order striking the original defence were upheld. Maplequest relied on Thrive Capital Management Ltd. v. Noble 1324 Queen Inc., where defendants who had been found in contempt later did enough to purge their contempt and were allowed to file a defence.
Justice Brownstone distinguished Thrive Capital on its facts. In that case, the court found that the defendants had sufficiently complied with the last-chance order to justify granting them another opportunity to defend the claim. By contrast, Associate Justice Josefo expressly found that Maplequest remained non-compliant with his peremptory last-chance order at the time of the motion. He was not applying a standard of perfection, but rather responding to persistent, serious and ongoing non-compliance. Allowing Maplequest to file a new statement of defence after the associate judge had finally resorted to striking its pleading would, in the Divisional Court’s view, undermine his order and the authority of the case-management process. The Court therefore declined to grant that alternative relief.
Absence of policy wording or contractual clause analysis
The decision is procedural and does not discuss insurance policies or specific contractual clauses in any detail. While the underlying dispute likely arose from commercial or real estate development arrangements between Maplequest and Primont, the appellate reasons do not analyze any policy language, contractual terms, or particular clauses. Instead, the focus is on the Rules of Civil Procedure, the principles governing documentary disclosure, and the sanctions available when a party repeatedly fails to comply with court orders. As such, there are no “policy terms” or clauses at issue in the sense of insurance or detailed contract interpretation within this judgment.
Outcome and monetary consequences
In its final disposition, the Divisional Court held that Associate Justice Josefo had applied the correct legal test, had properly assessed Maplequest’s conduct in light of the Falcon Lumber, Advanced Farm and Rimon jurisprudence, and had reached a conclusion that was open to him on the record. The Court found no palpable and overriding error and no disproportionality in striking both Maplequest’s statement of defence and its counterclaim. As a result, Maplequest’s appeal was dismissed, and the associate judge’s order striking its pleading remained in full force.
The Court then addressed costs. Pursuant to the parties’ agreement on costs of the appeal, Justice Brownstone ordered that Maplequest pay Primont costs in the amount of $16,000 inclusive. This decision does not specify the amount of any underlying damages or other monetary award arising from the main action; only the appellate costs figure is stated. Accordingly, the successful party in this proceeding is Primont Homes (Vaughan) Inc., which not only preserved the striking of Maplequest’s defence and counterclaim but also obtained an inclusive costs award of $16,000 on the appeal, with any additional damages or amounts awarded in the underlying litigation not determinable from this decision.
Download documents
Appellant
Respondent
Court
Ontario Superior Court of Justice - Divisional CourtCase Number
DC-25-00000710-0000Practice Area
Civil litigationAmount
$ 16,000Winner
RespondentTrial Start Date