Search by
Background and facts of the dispute
Beauward Immobilier inc. is a real estate company that owns an immovable located at 1075, boulevard Firestone in Joliette. It instituted a civil action in the Superior Court of Québec against MPA Groupe-Conseil inc., an engineering/consulting firm, seeking more than six million dollars in damages. The claim is based on alleged serious deficiencies in compliance with applicable seismic (parasismic) standards at the time of construction. Beauward alleges that MPA bears responsibility for grave non-conformities affecting the structural safety of the building, which were only uncovered after a detailed expert review of the structural plans. According to the judgment, the defects were discovered when Beauward received its experts’ report on 10 June 2021, following an in-depth review of the structural drawings. The originating application was filed with the Superior Court on 31 May 2024 and served on 4 June 2024. On its face, this timing placed Beauward close to the outer limits of the applicable prescription period under article 2894 C.c.Q., so that any further procedural misstep risking a deemed discontinuance could have the effect of making the action time-barred. As a corporation, Beauward is required under article 87 C.p.c. to be represented by a lawyer in contentious proceedings. Internally, its vice-president, legal affairs, Me Nathalie Parent (a member of the Québec Bar since 1995), worked together with external counsel, Me Alice Boivinet of Donati Maisonneuve, to advance the case. This included responding to an extensive request for pre-engagements from MPA’s counsel, comprising some 37 distinct items, which ultimately required the collation and transmission of more than 3,000 documents over several months.
Procedural history and the first extension
Under the original case protocol, the deadline for filing the joint declaration and request for setting down for instruction and judgment was 4 December 2024. That deadline was characterized as a strict or “délai de rigueur” under article 173 C.p.c. The file did not progress as it should have, and Beauward failed to file the required inscription by this date. It was in fact MPA’s counsel who notified Beauward’s counsel of this default. As a result, Beauward had to bring a first application under article 177 C.p.c. to be relieved from the deemed discontinuance and to obtain a new deadline. The Superior Court granted that first application and extended the deadline for the case to be set down to 6 June 2025. This new date was clearly recorded in the joint protocol filed by the parties, which noted 6 June 2025 as the inscription deadline.
The second error and missed deadline
Despite this, a new administrative mistake occurred within Beauward’s legal team. As described in Beauward’s plan of argument and oral submissions, a collaborator in Me Boivinet’s office mistakenly entered 30 September 2025 instead of 6 June 2025 as the inscription deadline for this case, effectively confusing it with another, related file (no. 500-17-128837-245). That related file involved: the same defendant MPA, related plaintiffs, the same defence counsel, similar parasismic-compliance allegations, and even a similar internal office file number. Relying on what she had been told, Me Parent states under oath that she operated on the basis that the inscription deadline was 30 September 2025, not 6 June 2025. During this same period, she devoted substantial time and internal resources to responding to MPA’s pre-engagement requests, mobilizing her teams, working with external counsel, and sending more than 3,000 documents in several tranches. As of early June 2025, all reasonable steps to respond to the pre-engagement requests had been completed, but the inscription itself was not filed by the true deadline of 6 June 2025. On 29 August 2025, at 16:12, MPA’s counsel emailed Beauward’s counsel, effectively flagging the missed deadline. Me Boivinet was then abroad on vacation and only saw the email on her return on 4 September 2025. She promptly contacted MPA’s counsel by telephone to discuss the situation and then, on 8 September 2025—less than a week after her return—filed the “Deuxième demande pour être relevé du défaut de produire une demande d’inscription pour instruction et jugement et en prolongation de délai.”
Positions of the parties on the second extension
MPA adopted a strict and uncompromising stance. It argued that by failing to respect a second strict deadline, Beauward was deemed to have discontinued its action under article 177 C.p.c., and that the court should refuse any further extension. According to MPA, article 177 allows a second extension only where “un motif impérieux / compelling reasons” exists—a standard it characterized as more exacting than the initial threshold of “impossibility in fact to act,” and one that Beauward had not met. MPA stressed that Beauward itself had shown no diligence in monitoring the 6 June 2025 deadline, that Me Parent’s sworn statement did not explicitly admit any error by the company or its counsel, and that it was silent about any steps taken by Beauward specifically concerning that date. On MPA’s reading, there was no clear and convincing evidence of a compelling reason justifying a second extension. Beauward, for its part, acknowledged the error as a clerical or administrative mistake by its lawyer, for which counsel remained professionally responsible. It relied on the detailed sworn declaration of Me Parent, the substantial work undertaken to respond to MPA’s pre-engagement demands, the serious nature and very high value of the claim, and the short lapse of time (under three months) between the expiry of the deadline and the second application. Beauward also highlighted that, as a corporation, it could not act in person before the courts and had done what a reasonable corporate litigant would do: it retained counsel, collaborated closely with them, and provided voluminous supporting documentation.
Legal framework: articles 20 and 177 C.p.c. and access to justice
The court situates this dispute within the broader objectives of the 2016 reform of the Code of Civil Procedure. It recalls the preliminary provision and article 20 C.p.c., which require parties to cooperate, inform each other of relevant facts, preserve evidence, and conduct litigation in a way that promotes accessibility, quality and speed of civil justice, and a just, simple, proportionate, and economical application of procedure. The judge stresses that lawyers are not merely representatives of private interests but also officers of the court who exercise a public function in the administration of justice. Article 177 C.p.c. is set out in full and interpreted in light of these principles. The provision establishes: (1) a presumption that the plaintiff is deemed to have discontinued the action if it fails to request setting down within the strict time limit; (2) a power for any other party—including the defendant—to file a request for setting down within 30 days of the expiry of the plaintiff’s deadline; and (3) a discretion for the court to relieve the plaintiff from the sanction where it was in fact impossible to act within the time limit, and then to fix a new deadline “which cannot be extended except for compelling reasons.” The court reads the “motif impérieux / compelling reasons” requirement as a factual, discretionary standard that must be applied case-by-case, taking into account all the circumstances, including the overarching aims of the reformed C.p.c.: access to justice, proportionality, cooperation, and the preference for resolving disputes on their merits rather than on purely technical or tactical procedural grounds.
Application to Beauward’s second request for relief from default
On the facts, the judge notes that refusing the second extension would almost certainly lead to the prescription of Beauward’s claim for more than six million dollars, given the operation of article 2894 C.c.Q., effectively extinguishing a serious claim without a hearing on its merits. Against that, there was no evidence of any irreparable prejudice to MPA if the case were allowed to proceed; its position was essentially strategic and based on a strict reading of the procedural rules. The court emphasizes several key elements: Beauward is a corporation that can only litigate through counsel; it had retained experienced lawyers and acted diligently in responding to extensive pre-engagements; its vice-president and internal teams worked intensively with external counsel to collect more than 3,000 documents; its counsel candidly admitted the clerical error in docketing the wrong deadline; and the delay between the expiry of the real deadline (6 June 2025) and the second application (8 September 2025) was relatively short. The judge also notes that MPA’s counsel knew the true deadline, knew that the case involved significant issues and a high quantum, and yet chose not to remind opposing counsel of the upcoming date, only raising the point afterward and resisting any consensual extension. This conduct is found to be at odds with the spirit of cooperation envisaged by article 20 C.p.c. and the preliminary provision.
Outcome, successful party, and monetary consequences
In light of these considerations, the Superior Court exercises its discretion under article 177 C.p.c. to find that there are compelling reasons to grant a second extension of time. The court allows Beauward’s “Deuxième demande pour être relevé du défaut,” formally relieves it from the deemed discontinuance that would otherwise flow from its failure to file an inscription before 6 June 2025, and extends the time for putting the case in a state of readiness and filing the request for setting down for instruction and judgment to 7 August 2026. The parties are given until 20 March 2026 to complete and file a new case protocol. As to costs, the judgment explicitly reserves them: “FRAIS DE JUSTICE à suivre.” No damages or other monetary relief is adjudicated at this stage; the underlying claim for more than six million dollars in alleged parasismic-related damages remains to be determined on the merits. Overall, the successful party in this procedural decision is Beauward Immobilier inc., which secures the continuation of its action and the lifting of the procedural default, but no specific monetary award, costs, or damages are granted or quantified in its favor in this judgment, and the total amount ordered in its favor therefore cannot yet be determined.
Download documents
Applicant
Respondent
Court
Quebec Superior CourtCase Number
500-17-130132-247Practice Area
Civil litigationAmount
Not specified/UnspecifiedWinner
PlaintiffTrial Start Date