Search by
Facts of the case
Groupe Lapalme inc., a company specializing in excavation and grading work, submitted a bid on April 7, 2026, in response to a February 16, 2026 call for tenders (No. 6603-26-0214) issued by the Ministère des Transports et de la Mobilité durable (MTMD) for the design-construction of a bridge over the Mathieu stream in La Tuque. The bidding process required submissions in two separate electronic files: one containing the quality demonstration and another containing the price. Under the process, the selection committee first evaluated quality without knowing the submitted price; only bids scoring at least 70 points on quality then had their price considered and adjusted according to their quality score. Groupe Lapalme mistakenly placed several documents that should have gone into the quality file into the price file instead. On April 30, 2026, Groupe Lapalme followed up with the MTMD about the status of its bid and was told the process was ongoing. On May 12, 2026, the MTMD informed Groupe Lapalme that its bid had been declared inadmissible and non-conforming because it was missing the Revenu Québec attestation and the Office québécois de la langue française document (both mandatory admissibility conditions), as well as the bid security and the bid form (both mandatory conformity conditions). The selection committee recommended awarding the contract to Les Entreprises Rosario Martel inc., whose bid ranked first with a score of 85/100, a submitted price of $4,200,000, and an adjusted price of $3,818,181.82. Groupe Lapalme's own unadjusted bid price was lower, at $3,000,726.50, though its price file was never opened or reviewed by the Ministry.
Policy and legislative provisions at issue
The case turned on the Bidding Instructions issued by the MTMD, particularly Article 24.2, which permits — but does not require — the Ministry to allow a five-day correction period for missing admissibility documents (the Revenu Québec attestation and the language office document), and Article 24.3, listing the mandatory admissibility conditions. Article 25.1, governing mandatory conformity conditions, states that failure to include the bid security or the signed bid form constitutes a major irregularity leading to automatic rejection, with no discretion granted to the Ministry. The court also applied the Règlement sur les contrats de travaux de construction des organismes publics, particularly Article 7, which similarly lists automatic rejection grounds, including the absence of a required security or of the document constituting the bidder's commitment.
Reasoning and analysis
The court applied the established test for a provisional interlocutory injunction: apparent right, serious or irreparable harm, and balance of convenience, per Groupe CRH Canada inc. c. Beauregard, plus urgency at the provisional stage, per Mouska Chanvre inc. c. Bergeron. Urgency was found to be met, since the Ministry was on the verge of awarding the contract to the third party. On apparent right, the court found Groupe Lapalme's position weakened by the mandatory nature of the conformity conditions: while Article 24.2 allows, without requiring, a correction period for admissibility documents, no equivalent discretion exists for conformity documents such as the bid security and bid form, whose absence triggers automatic rejection under Article 25.1. Since the price file was never opened by the Ministry, the fact that Groupe Lapalme's price was lower than the winning bidder's could not, on its own, establish an apparent right. On serious or irreparable harm, the court held that the alleged harm was speculative, since the bid was never substantively evaluated and there was no certainty it would have scored the minimum points required on quality for its price to even be considered; a claim for monetary damages also remained available as an alternative remedy, as recognized in a similar prior case, 9211-4560 Québec inc. c. Procureure générale du Québec. On balance of convenience, the court found this favored the Ministry, given that the bridge served as the sole maintained road link for the Obedjiwan community, with design acceptance due by October 25, 2026 and construction completion required by October 15, 2027, citing Martel Building Ltd c. Canada and Placement Prenium inc. c. Centre d'acquisitions gouvernementales for the principle that collective interest should prevail over private interest in public procurement.
Ruling and overall outcome
The Superior Court of Quebec dismissed Groupe Lapalme's application for a provisional interlocutory injunction, finding that none of the necessary criteria — apparent right, serious or irreparable harm, or balance of convenience — were satisfied. Les Entreprises Rosario Martel inc. remains the recommended awardee of the contract. Costs were awarded against Groupe Lapalme, the unsuccessful party, though no specific monetary amount for costs was stated in the judgment beyond the standard order for legal costs.
Download documents
Plaintiff
Defendant
Other
Court
Quebec Superior CourtCase Number
200-17-039113-261Practice Area
Administrative lawAmount
Not specified/UnspecifiedWinner
DefendantTrial Start Date