Search by
Facts of the case
For nearly twenty years, the restaurant "Les Folies" operated in commercial premises in Montreal owned by Lisa Administration et Services inc. ("Lisa Administration") and leased by 9134-8144 Québec inc. ("9134"). In the fall of 2018, the parties agreed to a joint renovation and expansion project involving excavation of the building's crawl space to create a basement kitchen. Under this arrangement, Lisa Administration was responsible for the excavation and basement structure, while 9134 was responsible for demolition, finishing the basement kitchen, and renovating the ground floor.
The restaurant closed temporarily at the end of October 2018 so the work could begin. Two lease addenda signed in December 2018 extended the lease term and adjusted rent abatements tied to the renovation schedule, but did not state an explicit completion date. Nonetheless, extensive correspondence, permit applications, subsidy documents, and a contract between Lisa Administration and its excavation contractor, Ardena Construction, consistently referenced a target completion date near the end of February 2019 for Lisa Administration's portion of the work, allowing 9134 to complete its own renovations in March and April 2019 and reopen in May 2019, ahead of the restaurant's busiest season.
Lisa Administration's excavation work was repeatedly delayed. Contributing factors included a container obstructing the excavation site, discovery of an inactive underground Hydro-Québec cable, and a water leak that damaged excavation equipment — together causing roughly a month of delay. Lisa Administration also pointed to unexpectedly dense rock encountered during excavation as a cause of further delay, arguing this amounted to force majeure. The excavation was not completed until October 24, 2019, with remaining plumbing and electrical work finished in November and December 2019 — roughly ten months behind schedule. On October 23, 2019, having lost key staff and facing an unsustainable closure period, 9134 terminated the lease and later sued Lisa Administration for damages. Lisa Administration counterclaimed against 9134 and, invoking guarantee clauses, against its shareholders Jimmy Ledoux and Valérie Lessard personally.
Policy and legislative provisions at issue
The court's analysis relied on several provisions of the Civil Code of Québec ("C.C.Q."). Article 1378 defines a contract as an agreement of wills, and article 1458 obliges parties to honour their contractual commitments, making a defaulting party liable for resulting harm. Article 1854 requires a landlord to deliver leased premises in good repair and ensure peaceful enjoyment throughout the lease, while article 1863 allows termination where a party's failure to perform causes serious harm to the other. Article 1470 sets out the force majeure defence, requiring an unforeseeable and irresistible event. On damages, articles 1607, 1611, and 1613 confirm a creditor's right to compensation for harm that is an immediate and direct consequence of the breach and was foreseeable when the obligation was contracted, while article 1616 addresses non-pecuniary loss. Articles 1618 and 1619 govern legal interest and the additional indemnity running from formal notice. The guarantee (suretyship) provisions, articles 2333, 2335, and 2341, were relevant to Lisa Administration's claim against the individual guarantors, and article 85 of the Code of Civil Procedure was cited regarding standing to claim damages on behalf of shareholders.
Reasoning and analysis
The court held that, although the lease addenda did not fix an explicit completion date, contractual obligations extend not only to what is expressly stated but also to what follows from the nature of the agreement, usage, equity, and law. Six converging pieces of evidence — early scheduling discussions, a government grant application stating a target completion date, a permit application, a meeting among the parties' contractors confirming a sequencing plan, the excavation contract's own completion clause, and the structure of the rent abatement itself — persuaded the court that the parties had agreed Lisa Administration would substantially complete its portion of the work by approximately the end of February 2019.
Turning to fault, the court found that delays attributable to 9134 (the container, the electrical cable, and the water damage) accounted for only about a month and did not explain the ten-month overrun. It rejected Lisa Administration's force majeure argument regarding rock density, finding that the presence of rock in that part of Montreal was well known, that Lisa Administration's own engineer and contractors were aware of the risk, and that inadequate testing was conducted before work began — meaning the difficulty was foreseeable rather than an unforeseeable and irresistible event. The court also noted repeated instances where Lisa Administration assured 9134 that work would be completed shortly, only to miss those self-imposed deadlines, and found the landlord's management of the project lacking in transparency and good faith.
On quantification, the court reviewed 9134's claimed renovation and reopening costs, allowing most items but rejecting an unsubstantiated claim for fixed costs and adjusting for inventory value already counted elsewhere and for equipment 9134 later resold. It preferred the business-valuation methodology of 9134's expert over that of Lisa Administration's expert, whose approach — which included an unusually large risk premium and an unexplained adjustment for the COVID-19 pandemic occurring after the relevant loss date — the court found less reliable, notably because it produced an implausible negative valuation for the business after renovation costs. Corporate moral damages claims by both 9134 and Lisa Administration were dismissed, as a corporation cannot experience subjective non-pecuniary suffering and neither party proved recoverable pecuniary losses of that nature. Because 9134 was found entitled to terminate the lease, the court also addressed, in the alternative, what Lisa Administration's damages and the guarantors' liability would have been had the termination not been justified.
Ruling and overall outcome
The court found that 9134-8144 Québec inc. was entitled to terminate its commercial lease with Lisa Administration et Services inc. due to the landlord's failure to complete its renovation obligations within a reasonable time, and it accordingly confirmed the October 23, 2019 termination. Lisa Administration's counterclaim and third-party proceedings against 9134's guarantors, Jimmy Ledoux and Valérie Lessard, were dismissed in their entirety. The court ordered Lisa Administration et Services inc. to pay 9134-8144 Québec inc. a total of $341,056.63 in damages — comprising $141,056.63 for renovation and reopening costs and $200,000 for loss of business value — plus legal interest and the additional indemnity under article 1619 C.C.Q. running from the September 20, 2019 formal notice, together with legal costs.
Download documents
Plaintiff
Defendant
Court
Quebec Superior CourtCase Number
500-17-110802-199Practice Area
Real estateAmount
$ 341,057Winner
PlaintiffTrial Start Date