• CASES

    Search by

Atkinsréalis Construction (Pacific) Inc. v. GIP Construction Ontario East Ltd.

Executive Summary: Key Legal and Evidentiary Issues

  • Section 13 of the Arbitration Act, 1991 lets a party ask the court to remove an arbitrator during a proceeding where circumstances may give rise to a reasonable apprehension of bias.
     
  • Fair and equal treatment under s. 19 is mandatory, and parties cannot contract out of an arbitrator’s duty of neutrality.
     
  • Questioning by an arbitrator can amount to impermissible cross-examination, and the arbitrator’s intention is not relevant to the bias analysis.
     
  • Prepared lines of leading questions put to two of ATRL’s witnesses were found to undermine ATRL’s case and the credibility of its witnesses.
     
  • Counsel’s limited contemporaneous objections did not defeat the challenge, because there was no finding that the application was brought for tactical reasons.
     
  • On the stay motion, the court adopted a strong prima facie case standard under s. 13(7), a higher threshold than a serious issue to be tried.
     


Facts of the case

Atkinsréalis Construction (Pacific) Inc. (ATRL) was the prime contractor on the Trillium Line Extension Stage 2 Project in Ottawa, and GIP Construction Ontario East Ltd. was its roadworks subcontractor. Project delays led to changes in the agreed scope and timing of work, and each side asserted claims against the other. The parties agreed to arbitrate several claims asserted by each of them in one proceeding. They appointed Stephen Richard Morrison, an arbitrator with specialized construction industry knowledge, knowing of his experience and his active style of conducting hearings.

At a prehearing conference in April 2025, the arbitrator told counsel he preferred a somewhat more inquisitorial approach, and both counsel agreed. Witness affidavits and expert reports were exchanged before the hearing, which began on December 8, 2025. On December 17, 2025, eight days into the hearing, ATRL asked the arbitrator to remove himself. By then, all fact witnesses had been examined and three days of expert testimony remained. In reasons dated April 18, 2026, the arbitrator dismissed the challenge, and on May 15, 2026, he ruled that the arbitration should be completed by the end of June 2026.

ATRL then applied to the Ontario Superior Court of Justice (Commercial List) to decide the issue. The application was heard on July 15, 2026, but did not finish and was set to conclude on September 22, 2026. With the arbitration scheduled to resume on October 5, 2026, for two or three days of expert evidence, ATRL moved for a stay, which the court heard on August 18, 2026.

Policy and legislative provisions at issue

Under s. 13(1) of the Arbitration Act, 1991, an arbitrator may be challenged where circumstances exist that may give rise to a reasonable apprehension of bias. If the parties do not agree to remove the arbitrator and the arbitrator does not resign, s. 13(5) requires the arbitrator to decide the challenge. Section 13(6) then gives the challenger ten days to apply to the court to decide the issue and remove the arbitrator. Section 13(7) permits the arbitration, including the challenged arbitrator, to continue while the application is pending “unless the court orders otherwise.” Section 19 requires that parties be treated equally and fairly, and s. 3 lists that obligation among the provisions parties cannot exclude by agreement.

The arbitrator also relied on para. 9 of his terms of appointment. That clause allowed the parties to cross-examine adverse witnesses and, recognizing that the arbitrator is a neutral adjudicator, entitled him to question any witness, including party-appointed experts. The parties in turn could ask follow-up questions on matters raised by his questioning.

Reasoning and analysis

On the stay motion, neither party could locate case law interpreting s. 13(7), so the court applied the common law test for stays, guided by the tripartite test in RJR-MacDonald Inc. v. Canada (Attorney General). Given the strong presumption of arbitral independence and the rarity of successful bias challenges, the court required a strong prima facie case rather than merely a serious issue to be tried. That threshold was met. The court was troubled by the arbitrator’s view that his questions could not be cross-examination by definition, since that reasoning would make it impossible for any judge’s questioning to cross the line. Requiring ATRL to appear before the arbitrator in light of that strong case was found to be irreparable harm, and with only a brief delay at stake, the balance of convenience favoured a short stay. In its August 19, 2026 endorsement, the court stayed the arbitration pending the outcome of the application.

On the merits, the court decided the issue afresh rather than as an appeal. It emphasized that no one questioned the arbitrator’s good faith and that ATRL’s counsel expressly did not allege actual bias. Relying on Szilard v. Szasz, the court held that arbitrators and judges are subject to the same principles on reasonable apprehension of bias. It also cited Vento Motorcycles, Inc. v. Mexico for the point that such a finding is a major breach that cannot be balanced away in commercial arbitration.

Transcripts showed the arbitrator conducting prepared cross-examinations of ATRL’s witnesses. With Mr. MacDonald, he first had the witness agree, in general terms, to a list of options for handling proposed changes that did not include termination, a major issue in the case. Later, he returned to those admissions to press the witness to accept that ATRL had taken none of those steps. Along the way he dismissed the witness’s concerns with remarks such as “You can argue about that” and “That might be a later fight” until the witness agreed. He also challenged the witness with an email that ATRL’s counsel objected had been misdescribed, at which point the questioning ended.

With Mr. Black, the arbitrator established that counsel had helped draft his witness statement and then described part of his evidence as “spin.” In contrast, GIP’s witness Mr. Faheem was not cross-examined on his lack of personal knowledge, nor was his evidence denounced as counsel’s spin, even though the arbitrator raised a similar concern about the affidavits.

The court rejected the arbitrator’s position that his questions were not cross-examination because he lacked any adversarial intent, holding that intention is irrelevant to whether a reasonable apprehension of bias arises. Neither the parties’ consent to an inquisitorial approach nor para. 9 of the terms of appointment authorized the arbitrator to cross-examine or set aside his duty of neutrality. The court also found the arbitrator’s treatment of ATRL’s alleged failure to object internally inconsistent, since he called it fatal in one passage and not fatal in another. In the court’s view, ATRL’s counsel had in fact objected in a measured way and brought the challenge while the evidence was still under way. Taken together, the cross-examinations could lead a reasonably informed observer to conclude that the arbitrator may have predetermined the outcome and may not decide the arbitration fairly.

Ruling and overall outcome

ATRL succeeded on both the stay motion and the application, and the court ordered the arbitrator’s removal under ss. 13(1) and 15(1) of the Arbitration Act, 1991. No monetary amount was awarded or fixed in either decision. Costs presumptively follow the event on a partial indemnity basis. If the parties cannot agree, ATRL may deliver written submissions on or before October 14, 2026, and GIP may respond on or before October 21, 2026. Those submissions cover the costs of this application and, if properly before the court, the recusal motion before the arbitrator.

ATKINSRÉALIS CONSTRUCTION (PACIFIC) INC.
GIP CONSTRUCTION ONTARIO EAST LTD.
Superior Court of Justice - Ontario
CL-26-00000307-0000
Construction law
Not specified/Unspecified
Applicant