Search by
Facts of the case
In 2014, Lorrelind Holdings Ltd. lent money for the MacEwan Grove Project, an Edmonton condominium development made up of duplexes. Bosecke & Associates, along with lawyers Carl Bosecke and Salvador Tinajero, acted as its counsel. After the borrowers defaulted, the firm commenced an action for Lorrelind in October 2017 to enforce the mortgage and guarantees securing the loan. The borrower and guarantors responding in that litigation were 1827956 Alberta Ltd., 1476403 Alberta Ltd., 1777043 Alberta Ltd., Harpreet Singh and Joginder Singh.
To resolve the dispute, the lawyers prepared a forbearance agreement effective November 27, 2017. A consent judgment was also obtained, which all relevant parties consented to on December 8, 2017, with the judgment amount left blank. On April 11, 2018, the lawyers obtained consent foreclosure orders for Units 5 and 6 of the project, and title passed to Lorrelind. When later payments under the forbearance agreement went unpaid, collection efforts continued.
The firm stopped acting in September 2019, citing a conflict of interest with the opposing parties, and Lorrelind retained new counsel. That counsel applied to enter the consent judgment. Opposing the application, the borrower and guarantors filed an amended brief on November 20, 2020, arguing that the foreclosure orders had extinguished the debt. An applications judge accepted that argument on July 18, 2023, and dismissed the application, and Lorrelind did not appeal.
Lorrelind sued its former lawyers for professional negligence on April 5, 2024, claiming more than $1.9 million and submitting that its damages were $2,007,427.29. Its allegations included acting in a conflict of interest, drafting ambiguous documents, entering the foreclosure orders, failing to follow instructions on and delaying the consent judgment, and failing to advise that foreclosure would extinguish the debt. Lorrelind applied for summary judgment, while the lawyers applied for summary dismissal on limitations grounds.
Policy and legislative provisions at issue
The forbearance agreement confirmed an outstanding debt of $1,811,046.39 and the mortgagor's default. It stated that, so long as neither the borrower nor the guarantors breached it, Lorrelind would accept the lesser sum of $425,000, exclusive of legal fees incurred afterward, as full satisfaction of the indebtedness. Payments were to be made in semi-annual instalments of $50,000, plus interest and legal fees, from June 30, 2018, to December 31, 2019, with the balance due March 31, 2020. The mortgagor and guarantors also agreed to provide consent foreclosure orders for Units 5 and 6, and Lorrelind agreed not to take further steps in the litigation while they were not in breach. According to the court, the agreement lacked clarity on what was intended for the balance of the debt after the foreclosure orders were entered.
Section 48(1) of the Law of Property Act provides that a foreclosure order vests title in the mortgagee free of the mortgagor's right of redemption and operates as full satisfaction of the debt secured by the mortgage. Under s 3(1)(a) of the Limitations Act, a defendant is immune from liability if the claimant does not seek a remedial order within two years after it first knew, or ought to have known, that the injury had occurred, that it was attributable to the defendant, and that it warranted a proceeding, assuming the defendant's liability.
Reasoning and analysis
Drawing on Canada Permanent Trust Company v. King Art Developments Ltd., 1984 ABCA 182, the court explained that in Alberta a mortgagee who acquires title through a judicial sale may still collect the balance owing on the covenant to pay, but one who acquires title through foreclosure cannot. No one disputed that the consent orders were foreclosure orders rather than orders for judicial sale.
Neither party suggested that the foreclosure orders were meant to extinguish the remaining debt. The injury was therefore the unintended extinguishment of the loan, which occurred when the orders were entered in April 2018; the 2023 ruling only confirmed it. That injury was attributable to the lawyers, who had drafted the forbearance agreement and the foreclosure orders.
Lorrelind's attempt to tie its injury to the consent judgment failed. The 2023 ruling dealt with the effect of the foreclosure orders, not with the blank amount or delay in entering the consent judgment, and none of those matters caused the debt's extinguishment. Citing Chuang v Fogler Rubinoff LLP, 2022 ONCA 440, Lorrelind also argued that it was entitled to rely on its lawyers' advice. The court accepted that principle only up to September 2019, when new counsel was retained. Evidence that the firm continued to provide services on other matters until May 2024 did not show continued reliance on its advice about the loan. Aseniwuche Winewak Nation of Canada v. Ackroyd LLP, 2023 ABCA 60, was distinguished: dismissal for long delay results from a constellation of events over time, whereas entry of the foreclosure orders was a distinct event that did not depend on a court finding.
Acknowledging the complexity of mortgage law, the court noted that the lawyers' own position made it unnecessary to decide whether Lorrelind ought to have known before November 20, 2020. On that date, the amended brief explicitly set out the extinguishment argument, giving Lorrelind knowledge of the material facts supporting a plausible inference of liability. Because the action was filed on April 5, 2024, more than two years later, it was out of time.
In the alternative, the court held that the record could not support a finding of negligence. Expert evidence on the standard of care was required, and neither Kostic v Thom, 2021 ABCA 406, nor 495793 Ontario Ltd. (Central Auto Parts) v. Barclay, 2016 ONCA 656, supported an exception, since extinguishment of debt under s 48 is a technical legal matter beyond an ordinary person's knowledge. An adverse inference from the lawyers' failure to tender evidence from Mr. Bosecke was declined, as no important facts were uniquely available to him compared with Mr. Tinajero, who drafted the forbearance agreement and handled enforcement.
Lorrelind's evidence of damages, a spreadsheet calculating the outstanding debt, was only a first step. It assumed full collection, although the record pointed to poor collection prospects, including a $601,824.54 judgment against guarantor Harpreet Singh, evidence that the second mortgage security was of no value, and Mr. Tinajero's evidence that he advised Lorrelind that collection was uncertain because the guarantors had no assets or active business. Valuation of Units 5 and 6 was also unresolved: Lorrelind applied a credit of $800,000, the appraisals totalled $1,114,000, and Lorrelind had not reduced the debt to the $425,000 compromise figure.
Ruling and overall outcome
The Court of King's Bench of Alberta granted the lawyers' application for summary dismissal, dismissed Lorrelind's application for summary judgment, and dismissed the action under s 3(1)(a) of the Limitations Act, leaving Bosecke & Associates, Carl Bosecke and Salvador Tinajero immune from liability. Neither negligence nor damages was determined, as the evidentiary record was insufficient on both. No amount was awarded to any party, and the decision does not address costs.
Download documents
Plaintiff
Defendant
Court
Court of King's Bench of AlbertaCase Number
2403 06686Practice Area
Civil litigationAmount
Not specified/UnspecifiedWinner
DefendantTrial Start Date