Facts of the case
Noushin Granfar owns unit 1002 in a strata building at 1485 Duchess Avenue in West Vancouver. The respondents, Starr Insurance, Allianz Canada, RSA Insurance, AIG Insurance, Lockton Companies and Westport Insurance (the Insurers), insure the strata corporation under a policy covering the building’s common property, Ms. Granfar’s personal property and additional living expenses (ALE).
On May 27, 2019, Ms. Granfar’s washing machine overflowed and caused water damage to her unit and the building’s common property. The Insurers attributed the flood to a malfunction of her machine, while she blamed a backup in the building’s drainage system; either way, the strata policy covered the damage. A second water incident followed on June 11, 2019, when a contractor working in the building caused more water to enter the unit. Ms. Granfar maintained that this second event did significantly more damage than the first and filed a separate claim for it.
The Insurers opened separate claims for both occurrences and appointed Crawford & Company as their independent adjuster. In an October 2, 2019 letter to the strata, Crawford said the damage from the June incident was minimal compared with the original loss, that any secondary damage would fall below the strata’s $10,000 water damage deductible, and that it was closing that claim.
Repair estimates came in from several contractors: Phoenix Restorations at $20,503.35, FirstOnSite Restoration at $33,420.63, Belfor Property Restoration at $40,349.52, and MBC Group at $48,906.99. After Ms. Granfar raised hazardous materials concerns, a Coast BC Hazmat report she commissioned found that lead in the interior paint was below Health Canada’s allowable level and that asbestos was present in kitchen sink mastic that had been removed and placed in a bedroom. The MBC estimate responded to that report, concluding that undisturbed materials need not be removed, and noted Phoenix’s confirmation that the entire unit was affected by the first incident, making it impossible to separate the damage between the two occurrences.
Ms. Granfar submitted a proof of loss on May 25, 2020 claiming $184,149.35, with no ALE component; it was rejected because it appeared to cover more than one occurrence and the amount was not fully supported. In December 2020, Crawford advised that, because she had refused in March 2020 to let Belfor proceed with repairs, the Insurers would pay her according to the MBC estimate. Crawford also said no further ALE would be paid beyond a one-time $7,500 payment already made. Subsequent testing confirmed no asbestos contamination, but the Insurers increased the settlement to cover removal of the sink and hazardous cleaning. Ms. Granfar rejected the offer and, in May 2021, delivered separate proofs of loss claiming $83,382.66 and $80,766.10. Crawford rejected both on June 4, 2021 and advised that the Insurers had elected to proceed with the statutory dispute resolution process (DRP). Since February 19, 2021, the Insurers had paid approximately $209,152.69 in indemnity funds to and on behalf of the strata, including a $26,524.03 advance paid to the strata toward the expected cost of restoring her unit.
Ms. Granfar then turned to the Civil Resolution Tribunal, which held on September 22, 2021 that it lacked jurisdiction over her claims against the Insurers. When she did not appoint a DRP representative, the Insurers petitioned the court, and in 2024 BCSC 1051 the court ordered the DRP to proceed. She appointed Ebrahim Forouzan as her representative, while John Valeriote of Crawford represented the Insurers. After the representatives failed to agree on an umpire, the Superintendent of the BC Financial Services Authority appointed James Minns on September 27, 2024.
Mr. Forouzan objected to the umpire’s fees and appraisal agreement and did not attend a January 23, 2025 case conference call. The hearing, first set for February 25, 2025, went ahead by Zoom on March 4, 2025. Ms. Granfar’s materials included a Banff Contracting repair estimate of $84,210 and an ALE figure of $35,649.65, although her representative submitted that it was not the umpire’s role to determine ALE. The Insurers put the replacement cost value of the property damage at $16,980 and argued no further ALE was warranted because she had frustrated the repairs.
The award, signed by the umpire and Mr. Valeriote, valued property damage at $9,781.40 actual cash value and $48,906.99 replacement cost value, demolition and emergency repairs at $74,500.64, HEPA abatement cleaning at $2,032.67, and ALE at $5,250 (three months at $1,750 per month). The contents claim was not appraised. Ms. Granfar filed her petition challenging the award on April 4, 2025.
Policy and legislative provisions at issue
The policy contained the mandatory Statutory Conditions prescribed by s 29 of the Insurance Act. Statutory Condition 11(1) provides that any disagreement over the value of the insured property, the value of property saved, the nature and extent of repairs or replacements, their adequacy, or the amount of the loss or damage must be determined through the Act’s dispute resolution process, whether or not the insured’s right to recover is disputed. Under Statutory Condition 11(2), no right to the process arises until a specific written demand is made and a proof of loss has been delivered.
Section 12 sets out the mechanics. Either party may demand the DRP in writing after proof of loss is delivered, and each side must appoint a representative within 7 days, with the two representatives appointing an umpire within 15 days. The court may appoint a representative if a party fails to do so, and the Superintendent may appoint an umpire if the representatives cannot agree. Under s 12(6), the representatives determine the disputed matters by agreement or, failing that, submit their differences to the umpire, and the written determination of any two of the three decides the matters.
Section 58 of the Administrative Tribunals Act governed the review. Findings of fact or law within a tribunal’s exclusive jurisdiction cannot be disturbed unless patently unreasonable, and questions of natural justice and procedural fairness turn on whether the tribunal acted fairly in all the circumstances.
Reasoning and analysis
Relying on Vandale v Wawanesa Mutual Insurance Co., 2015 BCSC 766, the court treated s 12 and Statutory Condition 11 together as a privative clause giving the umpire exclusive jurisdiction over valuation. Because the umpire’s decision was confined to valuing the loss, his findings were reviewable only for patent unreasonableness, while the fairness complaints were assessed against the factors in Baker v Canada (Minister of Citizenship and Immigration).
Most of Ms. Granfar’s fairness arguments rested on the premise that the DRP covered only the first occurrence and that the second caused distinct damage. The court accepted that the DRP was convened for the first occurrence and that some confusion arose because the Insurers never clearly told her that her unit would be fully restored under that claim. Still, the evidence did not support any separate damage from the second event. The MBC estimate had said as much in November 2020, the October 2019 Crawford letter had treated any secondary damage as falling below the deductible, and her own DRP submissions acknowledged the Insurers’ position that the first occurrence damaged the entire unit. With both proofs of loss before the umpire, the court found the MBC estimate he chose was comprehensive and would have fully restored the unit. Her objections, in the court’s view, stemmed from disagreement with the decision rather than the process.
On ALE, the court held that such disputes fall within Statutory Condition 11(1) because ALE is part of an insured’s loss. Citing Westland Insurance Company Limited v Pounden, 2021 BCCA 156, it found that carving ALE out of the DRP would defeat the process’s purpose of reducing litigation delay and cost, and that sending ALE disputes to court while the rest of the claim went to the umpire would be absurd. Her position that ALE should continue indefinitely pending resolution in her favour was not sustainable. The court noted that the hearing took place more than five years after the loss, with delays arising from her failure to cooperate and the steps she took to prevent the process from occurring. She also knew ALE would be addressed and made submissions on it, and a missing proof of loss does not always bar the DRP, particularly where an insured fails to cooperate.
The court acknowledged it was not clear why the umpire included the $74,500.64 Phoenix demolition and emergency repair costs, which were not in dispute, but found he likely did so because Ms. Granfar had included the Phoenix invoice in her materials, and nothing turned on it. Her reliance on Allstate Insurance Company of Canada v Stephen Robb, 2023 NBKB 212, to argue the DRP should have paused for her pending court application failed, as that case involved a court application required by New Brunswick legislation to appoint an umpire, a role the Superintendent fills in British Columbia. Her claimed legitimate expectation that the DRP would cover only the first occurrence was likewise rejected, since the umpire’s mandate came from the statute and she had no ability to narrow it.
Arguments that she lacked a meaningful opportunity to participate also failed. Her representative had declared himself unavailable for the case conference without offering alternatives, which the court saw as part of a pattern of delay, and the umpire followed up with a detailed email and allowed further conferences on request. An oral hearing was, if anything, fairer than proceeding on written materials. The court accepted there was confusion over when Ms. Granfar’s brief was received, noting that Mr. Valeriote’s February 24, 2025 email said he had none while his May 21, 2026 affidavit said he received it on February 18, 2025. It inferred the February 25 hearing was adjourned because the Insurers missed the February 18 deadline, and found the adjournment resolved any confusion. Any concern about preparation time should have been raised with the umpire.
On reasons, the court found no British Columbia authority directly on point and adopted Madhani v Wawanesa Mutual Insurance Company, 2018 ONSC 4282, which held that the absence of reasons did not deny procedural fairness because the appraisal process values a loss rather than determining legal rights, is not adjudicative, and is not governed by a statutory requirement to give reasons. The DRP is not an arbitration, and the award is fixed by the written determination of any two of the three participants. The record showed the umpire’s rationale: he accepted the highest estimate the Insurers had produced, rejecting their lower proposed figures, while the MBC estimate he adopted explained why Ms. Granfar’s much higher estimate should not be accepted. He also awarded some ALE despite the Insurers’ position that none was owed.
The bias allegations, based on prior professional dealings between Mr. Valeriote and the umpire and on the umpire’s rejection of a preferred vendor’s scope of work, did not meet the reasonable apprehension of bias test. Repeat involvement in dispute resolution proceedings was unsurprising given their specialized expertise, and the suggestion that the umpire was searching for reasons to favour the Insurers was pure speculation.
Turning to patent unreasonableness, the court found Ms. Granfar largely repeated her fairness arguments. Including the undisputed demolition costs had no connection to the value assigned to her loss, and her objection that the Insurers’ estimates provided only for reinstalling her existing toilet rather than replacing it did not make the award patently unreasonable. Under s 12(6), the umpire’s role was effectively to choose from the amounts each representative presented, with the outcome decided by a two-thirds majority, and there was an evidentiary basis for his choices.
Ruling and overall outcome
The Supreme Court of British Columbia dismissed the petition, finding that Ms. Granfar had established neither a denial of procedural fairness nor a patently unreasonable award. As the successful parties, the Insurers were awarded their costs at scale B, though the decision does not state a dollar amount for those costs.
Download documents
Respondent
Petitioner
Court
Supreme Court of British ColumbiaCase Number
S252669Practice Area
Insurance lawAmount
Not specified/UnspecifiedWinner
RespondentTrial Start Date