Facts of the case
On June 20, 2012, Fraser Health Authority (FHA) entered into a contract with design-builder VanMar Constructors 1043 Inc. (VanMar) for the design and construction of a long-term care home in Mission. The agreement was a standard form design-build stipulated-price contract created by the Canadian Contractors Association (Document 14-2000), which the parties modified through negotiated “Supplementary Conditions.” VanMar then contracted with Trilar Fire Protection (Trilar) to design and construct the facility’s fire suppression system, and Trilar in turn hired Tru-Line Technologies Ltd. (Tru-Line) to provide fire suppression and engineering services. Tru-Line was not a party to the main contract.
Construction was substantially completed in 2014. According to FHA, a fire sprinkler line in the facility’s attic cracked in January 2020 and caused water damage, which FHA attributes to improper installation and insulation by Tru-Line and by Community Fire Prevention Ltd., the company responsible for inspecting and maintaining the fire protection and fire sprinkler systems. On September 26, 2022, FHA sued both companies, alleging negligence and breach of contract.
Tru-Line filed an application for summary judgment under r 9-6 of the Supreme Court Civil Rules on November 1, 2024, seeking dismissal of the claim on the basis that it fell within the phrase “all other consultants” in the contract’s waiver clause. After a hearing on January 30, 2025, the chambers judge of the Supreme Court of British Columbia dismissed the application on February 28, 2025 (2025 BCSC 334). Tru-Line appealed, and the Court of Appeal for British Columbia heard the matter on February 13, 2026.
Contractual provisions at issue
The dispute centred on GC 12.2.1, under which, as of the date of the final certificate for payment, the Owner “expressly waives and releases the Design-Builder, the Consultant, all other consultants, all Subcontractors, all Suppliers, and their agents and employees from all claims against them,” including claims arising from negligence or breach of contract, subject to certain exceptions. The contract named FHA as the Owner, VanMar as the Design-Builder, and KMBR Architects Planners Inc. and Farrow Partnership Architects Inc. as the Consultant. “All other consultants” was not defined.
Other defined terms were tied to the design-builder. “Consultant” referred to an entity “engaged by the Design-Builder” to provide its design services and to coordinate the design services “of all other consultants employed by the Design-Builder.” A “Subcontractor” and a “Supplier” were each defined as a person or entity having a direct contract with the design-builder. Under GC 3.7.1, the design-builder had to enter into contracts or written agreements with the Consultant and other consultants requiring them to perform their services as set out in the contract documents, and was made fully responsible to the Owner for the acts and omissions of the Consultant, other consultants, Subcontractors, Suppliers, and “persons directly or indirectly employed by them.”
Changes made by the Supplementary Conditions also reached the indemnity provisions. The design-builder’s indemnity in GC 12.1.1 was replaced with a clause referring to “Sub-Consultants,” a capitalized term not defined in the definitions section of the Supplementary Conditions, instead of “all other consultants.” That original phrase remained unchanged in the Owner’s indemnity in GC 12.1.3 and in the waiver itself. Insurance obligations under GC 11.1.1 were modified as well, with the design-builder’s obligation referring to “Sub-Consultant(s) and their respective servant(s), agent(s) or employee(s).”
Reasoning and analysis
Both parties had jointly submitted that a correctness standard applied. The Court of Appeal disagreed, holding that because certain modifications to the standard form contract had interpretive significance for the waiver, its interpretation was a question of mixed fact and law reviewable only for palpable and overriding error. Relying on Ledcor Construction Ltd. v Northbridge Indemnity Insurance Co., 2016 SCC 37, and 601 Main Partnership v Centura Building Systems (2013) Ltd., 2024 BCCA 76, the court explained that where modifications are relevant to the interpretive issue, the interpretation is unique to the parties and deference applies.
Like the chambers judge, the court accepted that “all other consultants,” standing alone, is broad, unqualified and inclusive, but held that it had to be read in the context of the contract as a whole. The chambers judge had not addressed the substitution of “Sub-Consultants” in GC 12.1.1, and the court found that replacing the phrase in the design-builder’s indemnity, but not in the Owner’s indemnity or the waiver, suggested the two terms meant different things. Within the contract, “other consultants” is sometimes qualified as those employed or retained by the design-builder and sometimes left unqualified. Reading the relevant sections together, informed by the Supplementary Conditions, the court concluded that the contract contemplates two types of consultants: the primary Consultant and other consultants retained by the design-builder. Since “Subcontractor” and “Supplier” are limited to entities in a direct contract with the design-builder, “other consultants” was read the same way, which also made the waiver internally consistent because every entity it lists shares a like relationship with the design-builder.
Several other provisions pointed in the same direction. Clauses on delays (GC 6.5.2) and the design-builder’s right to suspend work (GC 7.2.2) refer to persons directly or indirectly employed or engaged by the design-builder, and GC 3.7.1 extends the design-builder’s responsibility to persons directly or indirectly employed by the listed entities. According to the court, the absence of that expansive language in the Owner’s waiver tended to support the inference that “all other consultants” has a more limited scope. Under GC 6.3.4.6, the design-builder must keep an itemized accounting of the costs of a change, including the fees and disbursements of the Consultant or other consultants engaged or employed to provide such services, and the court reasoned that it could meaningfully account only for other consultants with whom it has a direct relationship. The design-builder’s broader insurance obligation likewise appeared to support it having wider responsibility than the Owner for lower-tier consultants. Taken together, and informed by the modifications, these features showed a mutual intention to place on the design-builder the risk of managing the entities it retains or employs, in exchange for which the design-builder and the entities it directly retains or employs benefit from the waiver.
While accepting that GC 3.7 is not determinative, since it uses “other consultants” rather than the disputed phrase, the court found it informative. The Owner enforces the contract through obligations on the design-builder, whose contractual supervision and control are limited by privity to the agreements it executes with others, so when a directly retained consultant engages an outside consultant, the Owner’s and design-builder’s ability to supervise and control that work is undermined.
On commercial reasonableness, the court rejected FHA’s broad argument that a contract is only commercially reasonable if there is “mirror reciprocity” between its indemnification clauses and any waiver, but found it logically coherent that the Owner’s waiver would mirror the scope of its indemnity and insurance obligations, which appear more limited than those of the design-builder. In the context of this particular arrangement, waiving claims against the broader group of entities would not be logical or commercially sensible for the Owner, which has no contractual relationship with a lower-tier consultant and no meaningful ability to supervise and direct its work. Commercial reasonableness, the court noted, is assessed from the standpoint of each party to a contract (Resolute FP Canada v Ontario (Attorney General), 2019 SCC 60). The word “all” can reasonably be read as capturing all directly engaged consultants, in the same way the waiver refers to “all Subcontractors” and “all Suppliers.”
Tru-Line’s privity argument failed as well. Under the principled exception set out in Fraser River Pile & Dredge Ltd. v Can-Dive Services Ltd., [1999] 3 SCR 108, the question is whether the contracting parties intended to extend the benefit to the third party and whether the third party’s activities are the very activities contemplated by the contract or the provision. Because the waiver covers only consultants engaged by the design-builder, the parties could not reasonably be said to have intended to extend its benefit to Tru-Line. Tru-Line therefore failed the first branch of the test, and the chambers judge had correctly decided the issue.
Ruling and overall outcome
The Court of Appeal for British Columbia dismissed the appeal on October 15, 2026, finding no palpable and overriding error in the chambers judge’s interpretation of “all other consultants” as limited to consultants directly engaged by the design-builder. FHA prevailed, with Tru-Line’s attempt to have the claim against it dismissed through summary judgment rejected at both levels. The decision does not address costs, and no damages or other monetary amount was ordered or awarded.
Download documents
Appellant
Respondent
Court
Court of Appeals for British ColumbiaCase Number
CA50555Practice Area
Construction lawAmount
Not specified/UnspecifiedWinner
RespondentTrial Start Date