Search by
Facts of the case
Byno Belhocine, a salesperson and self-employed worker, was retained by Consultations G.E.M.S. Inc. (GEMS) on or about August 1, 2023, to sell the services of Cogeco Connexion Inc. (Cogeco). He was paid on commission. Two months later, GEMS ended his mandate.
On November 8, 2023, Belhocine sent a formal demand letter to Cogeco seeking payment for sales made before September 27 and compensation for the week he was taken off work, from September 27 to October 6. In a text message, GEMS committed to paying him $3,132 and then tried to send a first instalment of $2,500 by Interac transfer, which he refused because he wanted a cheque. At his request, the transfer was cancelled, and he was told GEMS would prepare a cheque and have him sign a document confirming payment of the pay report. A representative later offered to give him the cheque at the office at 3:30 and, when he asked to receive it by mail, replied that he would have to come in on Monday if he chose the cheque. Belhocine refused to travel, and the payment was never made.
He filed a small claims application on April 19, 2024, seeking $11,892.50 from both defendants. The claim was made up of $4,872.50 in unpaid commissions and bonuses, $2,520 in lost earnings on clients he had convinced before his dismissal, $2,000 for termination without reasonable notice, and $2,500 in moral damages for stress, trouble and inconvenience. Cogeco denied liability in its May 14, 2024 defence and argued that no legal relationship existed between it and the plaintiff. GEMS filed a written defence but did not appear at the March 9, 2026 hearing, despite being duly summoned and contacted by telephone and email before and during the hearing. The matter was heard by one judge and later continued and decided by another with the parties’ consent.
Policy and legislative provisions at issue
No contractual clauses were quoted in the decision. The court relied on the service documents signed by Belhocine and GEMS representative Jérémie Vincent on August 1 and 2, 2023, to identify the parties to the contract. Several Civil Code of Québec provisions shaped the outcome. Article 2125 gave GEMS the right to unilaterally resiliate the contract, and article 2129, paragraph 1, was the basis on which the court found the $3,132.50 owed. Article 1566 provides that payment is made at the debtor’s domicile. Article 1619 governs the additional indemnity added to the award.
Reasoning and analysis
Cogeco was cleared because no contract linked it to the plaintiff. Documents signed on August 1 and 2, 2023, showed that the service contract was formed between Belhocine and GEMS, a point confirmed at the hearing by Jonathan Laberge of Cogeco.
As against GEMS, the court found that the company had admitted owing $3,132.50 in commissions, relying on exhibits P-10, P-11 and D-2. Article 2125 C.C.Q. gave GEMS the right to unilaterally resiliate the contract, and the court held that the $3,132.50 represented the sum owed under article 2129, paragraph 1. In the circumstances, it found the plaintiff was not entitled to the $2,520 for lost earnings or the $2,000 for lack of reasonable notice. His $2,500 claim for stress, trouble and inconvenience was also rejected, since he himself had ended the settlement process that GEMS initiated in November 2023 but could not complete. Finally, the court recalled that, under article 1566 C.C.Q., payment is made at the debtor’s domicile.
Ruling and overall outcome
The court dismissed the claim against Cogeco Connexion Inc. without costs and allowed the claim against Consultations G.E.M.S. Inc. in part. Belhocine was awarded $3,132.50, plus interest at the legal rate and the additional indemnity under article 1619 C.C.Q. from the date of service, along with legal costs. The judgment gives no dollar figure for the interest, indemnity or costs.
Download documents
Plaintiff
Defendant
Court
Court of QuebecCase Number
500-32-165385-248Practice Area
Civil litigationAmount
$ 3,133Winner
PlaintiffTrial Start Date