McMaster Custom Builder Ltd. v 1276770 B.C. Ltd.

Executive Summary: Key Legal and Evidentiary Issues

  • McMaster Custom Builder Ltd. sought summary judgment under Rule 9-7 for $180,446.45 in unpaid invoices under a cost-plus 13% construction contract, plus contractual interest at prime plus 4% per annum.
     
  • 1276770 B.C. Ltd. argued the claim was unsuitable for summary determination because it was intertwined with its $924,172.29 counterclaim for defects, delay and alleged improper billing, already set for an eight-day trial.
     
  • For the purposes of the application, the court rejected 127’s assertion that the contract was fixed-price, finding it inconsistent with 127’s own admissions and pleadings.
     
  • McMaster’s decision to pour a full basement instead of the 4-foot crawl space shown in the engineered drawings rested on an undocumented oral authorization from 127’s late principal, which the court viewed with some doubt.
     
  • Admissibility of 127’s Timberline Report, which put repair costs at $481,700, was contested, but the court declined to exclude it entirely when assessing suitability.
     
  • Concerns about litigating in slices and inconsistent findings led the court to dismiss the application as unjust and send both the claim and counterclaim to trial together.
     


Facts of the case

McMaster Custom Builder Ltd. (McMaster), a British Columbia general contractor operating since 2006, built a custom home for 1276770 B.C. Ltd. (127) on property at 1950 Sidmouth Road, Shelter Bay, British Columbia. Phil DeBarros, 127’s sole director and majority shareholder, dealt directly with McMaster’s principal, Mr. Higgins. Mr. DeBarros has since died, and his widow, Ms. Davey, a 49 percent shareholder, now acts as 127’s director as administrator of his estate.

In February 2022, McMaster provided a first budget of $888,317.52 excluding taxes ($994,915.62 including taxes), which included a 13 percent contracting fee and several placeholder figures. The parties signed a written agreement on or about June 5, 2022. Later that month, after Mr. DeBarros said his lender needed “fixed price” language, Mr. Higgins prepared a second budget of $1,056,658.93 including taxes, labelled Schedule “B.” Ms. Davey admitted she had not seen it before the litigation began.

Construction ran from August 2022 to January 2024, roughly 16 months rather than the nine months the agreement contemplated. The Columbia Shuswap Regional District issued an occupancy permit on December 27, 2023. According to Mr. Higgins, whose evidence on this point was not materially denied, Mr. DeBarros and Ms. Davey began living in the house on or about January 3, 2024. On January 19, 2024, 127 made its last payment of $200,000. Mr. Higgins was notified on February 29, 2024 that Mr. DeBarros had passed away, and the contractual inspection never took place.

McMaster’s final invoice of $7,898.57 brought total invoicing to $1,425,446.45. Against payments of $1,245,000, McMaster claimed $180,446.45 outstanding, a figure that excludes windows 127 paid for directly at a cost of approximately $190,000. McMaster sued on March 7, 2024, and 127 counterclaimed on August 22, 2024. As at September 1, 2026, McMaster put its claim, inclusive of contractual interest, at $221,966.21, with interest continuing at $41.77 per day. The application was heard September 1 to 3, 2026, with a full trial scheduled for the week of November 30, 2026.

Policy and legislative provisions at issue

Under the agreement, as admitted by 127 in response to a notice to admit, McMaster would build the house on a cost-plus 13% basis plus GST and PST. Payment was due within ten days of an invoice, with interest on overdue amounts at the Bank of Canada prime rate plus 4% per annum. Once the house was ready for occupancy, the parties were to hold an inspection and record any omissions or defects on a deficiency list. Taking possession would conclusively prove completion except for listed items, which were to be fixed within 30 days, and the parties were to use good faith efforts to agree on a holdback pending repairs.

Rule 9-7(15) of the Supreme Court Civil Rules allows the court to grant judgment unless it cannot find the necessary facts or it would be unjust to decide the issues summarily. 127 had also made an oral application under Rule 9-7(11)(b) at the outset to have the application dismissed as unsuitable. Costs were addressed under Rule 14-1(9), which presumptively awards costs to the successful party.

Reasoning and analysis

At the outset, the court allowed the application to proceed, noting it is rare to decide suitability without the full summary trial record, but warned McMaster of a possible adverse costs award. It found 127’s argument that the agreement was a fixed-price contract to be without merit for the purposes of the application, since it conflicted with 127’s own admissions, pleadings and counterclaim.

On the law, the court summarized that a contractor suing on a building contract must prove its terms and the amounts owing. It considered both the Saskatchewan Court of Appeal’s three-part burden-shifting test in Ace Burger Ltd. v G and I Construction Group Inc. and the “heavy burden” approach in Shaheen Custom Homes Ltd. v Brennan, without needing to choose between them. A contractor is entitled to payment once work is substantially complete, even with defects, and judgment may be granted despite an arguable counterclaim. However, where a counterclaim is inseparably connected to the claim and goes to its root, enforcing the claim alone may be manifestly unjust.

Several evidentiary weaknesses emerged on both sides. Regarding the full basement, the court found it strained reasonable belief somewhat that two knowledgeable industry participants would not at least have tried to obtain a quote for the planned crawl space, or exchanged anything in writing, before the foundation was poured. McMaster’s claim that a basement was cheaper also lacked supporting documents. Ms. Davey was in a disadvantageous position, having not been party to many key discussions, but the court held this did not excuse the lack of precision in affidavit paragraphs that simply referred to “we” and “us.” Turning to 127’s evidence, its claim for lost rental income of $71,631.22, which was not before the court for determination, rested on a profit and loss statement prepared by an unidentified person without supporting documents.

The largest dispute concerned the Timberline Report, which put repair costs at $481,700, while McMaster’s responding Byl Report estimated remediation at $25,920, a difference of $455,780. Although the court acknowledged that the Timberline Report had identifiable defects and that its author was plainly not a professional expert witness, it would not exclude the report entirely for the purposes of assessing suitability.

Weighing the Gichuru v Pallai factors, the court found litigating in slices a real concern even under the “intertwined issues” approach from Ferrer v 589557 B.C. Ltd. The matter was more complex than McMaster suggested, and findings made on the application risked conflicting with those of the trial judge. Mr. DeBarros’s death did not mean the evidence was as good as it would ever be, as parts of the record were potentially open to cross-examination. With 127 asserting that McMaster owed it more than $900,000, the amount in dispute was significant. Judgment would not materially shorten the counterclaim trial, there was no urgency with trial about two months away, and McMaster faced no prejudice from delay because it held a certificate of pending litigation on the property.

Ruling and overall outcome

The Supreme Court of British Columbia dismissed McMaster’s application, finding it unjust to grant summary judgment as sought. It equally rejected 127’s position that McMaster had failed to prove its claim and that only the counterclaim should go to trial, ordering instead that McMaster’s claim and 127’s counterclaim proceed to trial together. Because 127 persuaded the court that granting the relief would be unjust, it was found substantially successful and awarded its costs in any event of the cause, not payable forthwith and to be assessed on Scale B if necessary. No dollar amount was fixed for those costs.

McMaster Custom Builder Ltd.
Law Firm / Organization
Pushor Mitchell LLP
Lawyer(s)

Mark Danielson

1276770 B.C. Ltd.
Law Firm / Organization
Not specified
Lawyer(s)

B.S. Coen

Supreme Court of British Columbia
S18248
Construction law
Not specified/Unspecified
Defendant