Facts of the case
Rather Be Plumbing Ltd. began providing plumbing and gas fitting services in or around September 2020 on a time and materials basis at a property at 3980 Goldstream Heights, Victoria, owned by Curtis Kimber and Carolyn Wotherspoon. Although both defendants owned the property, the parties agreed that Mr. Kimber contracted for the work. He described the project as the completion of a new rancher-style home, and the plumbing had been started by others before the plaintiff became involved. The scope was never put in writing, and the parties described it differently, but it was common ground that the plaintiff ran water and gas lines, installed or relocated fixtures, and attempted to install a boiler system and a jacuzzi tub.
Work proceeded on a near-daily basis from September 21 to December 10, 2020, with three further days from January 11 to 13, 2021. On or about January 13, 2021, the plaintiff issued an invoice for $36,947.28. Mr. Kimber testified that he was surprised by the amount and told the plaintiff he did not intend to pay it. According to Mr. Hughes, the plaintiff then lowered its hourly labour rate from $85 to $65, producing a revised invoice of $29,525.60. Mr. Kimber paid nothing toward either invoice. The plaintiff filed a claim of builder’s lien on May 14, 2021, stating that $29,525.60 became due on February 25, 2021, and commenced this action on July 16, 2021. Mr. Kimber counterclaimed for $41,289.45 in remedial costs, alleging the work was incomplete, defective, and outside the agreed scope.
Ms. Wotherspoon filed no response to civil claim and was ruled not entitled to defend at trial. Several of Mr. Kimber’s documents were excluded because they had not been disclosed under Rule 7-1(1) of the Supreme Court Civil Rules. During closing submissions, plaintiff’s counsel admitted she had failed to lead the evidence needed to support the lien claim. To keep the process fair, the court allowed both sides to reopen their cases, and the trial resumed on July 20, 2026.
Policy and legislative provisions at issue
Under s 20(2)(b) of the Builders Lien Act, a claim of lien must be filed no later than 45 days after the improvement is completed or abandoned. Section 1(5) deems a contract or improvement abandoned after 30 days without work, unless the stoppage was caused by a strike, lockout, sickness, weather, holidays, a court order, a material shortage, or a similar cause. Citing McManamna v Farley, 2008 BCCA 471, the court treated this as a rebuttable presumption that applies where the parties’ intentions are uncertain. A lien not filed in time is extinguished under s 22.
Other provisions included the Court Order Interest Act, which governed the plaintiff’s claim for prejudgment interest, and Rule 14-1(10) of the Supreme Court Civil Rules. That rule bars a plaintiff who recovers an amount within Provincial Court jurisdiction from costs other than disbursements, unless there was sufficient reason for bringing the case in the Supreme Court.
Reasoning and analysis
On the lien, the plaintiff relied on evidence from Jarod Hughes, one of its owners, given after the case was reopened. He said an employee tried to access the property near the end of February 2021 and that he texted Mr. Kimber on March 29, 2021 about returning to finish the job. The court rejected this. In his first testimony, Mr. Hughes had said the plaintiff stopped work on January 13, 2021 because of non-payment, he gave no explanation for the new account, no text message was produced, and the timeline aligned almost exactly with the Builders Lien Act deadline. His evidence about the employee’s failed attempt to gain access was also inadmissible hearsay. The court likewise refused to read Mr. Kimber’s closing remarks as a concession that the plaintiff had not abandoned its work, finding they related only to the overall state of construction and his own plans.
Having found that work ended on January 13, 2021, the court held the plaintiff was deemed to have abandoned the work on February 12, 2021. The filing deadline therefore fell on March 29, 2021, and the May 14, 2021 lien was extinguished.
The contract claim fared better. Mr. Kimber’s allegations of broad deficiencies had no support in admissible expert evidence, photographs, or third-party reports. Katie Whiting’s qualifications were never established, and while Edward McLean testified that he is a qualified plumber, nothing showed that the work either witness observed had been done by the plaintiff; their proposed opinions would in any case have been inadmissible expert evidence. Uncontroverted evidence that some of the plaintiff’s work passed Capital Regional District and gas inspections pointed the other way.
Mr. Kimber’s testimony that about $10,000 of the invoiced work was never done, however, went unchallenged. There was no evidence that Mr. Hughes was present during the work or verified it beyond confirming his employees’ reported hours, and the plaintiff pointed to no timesheet entries showing that the disputed work was performed. Mr. Kimber, on the other hand, had observed the project’s progress throughout and received the invoices. The court accepted his estimate as the best available evidence and deducted it from the revised invoice.
The counterclaim failed because Mr. Kimber proved neither that the plaintiff caused any defects nor what repairs would cost, and the court noted that the estimates in a counterclaim are not themselves evidence. As for Ms. Wotherspoon, nothing showed she contracted with the plaintiff or took on any personal obligation for the debt.
On interest, the plaintiff abandoned its claim for contractual interest but still sought prejudgment interest under the Court Order Interest Act. The court said such interest could not rest solely on a general prayer for further relief. Since the notice of civil claim sought $29,525.60 “including” interest and the award was substantially lower, adding prejudgment interest kept the total well below the pleaded amount and caused Mr. Kimber no prejudice. On costs, the court applied Grenier v Williams, 2020 BCSC 1827, and found the plaintiff had reasonable grounds to sue in the Supreme Court, the only forum for lien remedies, even though its recovery fell within Provincial Court jurisdiction.
Ruling and overall outcome
The Supreme Court of British Columbia dismissed all of Rather Be Plumbing Ltd.’s claims under the Builders Lien Act, Mr. Kimber’s counterclaim, and the claim against Ms. Wotherspoon. The plaintiff succeeded in contract and obtained judgment against Mr. Kimber for $19,525.60, along with prejudgment interest under the Court Order Interest Act from February 25, 2021 to the date of judgment, the amount of which the decision does not quantify. It was also awarded Scale B costs, excluding those tied to the July 20, 2026 continuation, again without a stated figure. The parties may seek directions on releasing the funds held in trust in place of the lien if they cannot agree.
Download documents
Plaintiff
Defendant
Court
Supreme Court of British ColumbiaCase Number
S212115Practice Area
Construction lawAmount
$ 19,526Winner
PlaintiffTrial Start Date