Facts of the case
Hoda Rahmani hired MNG Builders Inc. and Nima Rezaee Moghaddam to renovate her condominium in 2021 and 2022. Mr. Rezaee Moghaddam had been friends with her brother, Hatef Rahmani, for about 10 years. The renovation took longer than Ms. Rahmani wished, and she was not satisfied with the work. At the end of the job, she withheld payment in an amount that remains disputed, and Mr. Rezaee Moghaddam made a claim for $20,120.17. Ms. Rahmani maintained that she had paid everything owing and that remediation costs for deficient work should be offset. For his part, Mr. Rezaee Moghaddam said he received lists of deficiencies immediately after completing the work and fixed every issue identified.
On October 9, 2025, a Provincial Court of British Columbia judge found in Mr. Rezaee Moghaddam’s favour, awarding him the full amount of damages claimed for breach of contract. Because the parties’ written records were lacking, the trial judge had to decide the case on oral testimony, relying largely on her assessment of the parties’ credibility and reliability. Ms. Rahmani appealed to the Supreme Court of British Columbia. She asked the court to reverse the decision and remit the matter for a new trial or, alternatively, to order a different amount of damages. Her brother had assisted her at trial without testifying. Through a preliminary application, she sought to add him as an appellant. The court was given no basis for adding him but allowed him to participate in the appeal as her agent or representative. No affidavit or summary of proposed new evidence from him was provided, and nothing persuaded the court that fresh evidence was justified under R. v. Palmer.
Policy and legislative provisions at issue
The decision does not set out any written contract terms, and the court observed that both parties had deficient documentation of their professional arrangement. The appeal turned instead on the Small Claims Act, RSBC 1996, c 430. Section 5 allows a party to appeal a Provincial Court order allowing or dismissing a claim to the Supreme Court. Under s 12, an appeal may review questions of fact and law but must not proceed as a new trial unless the court orders it. Section 13(1) empowers the Supreme Court to make any order the Provincial Court could make, impose reasonable terms and conditions, make any additional order it considers just, and award costs in accordance with the Supreme Court Rules.
Findings of fact can be reversed only for a palpable and overriding error, while questions of law are reviewed for correctness. According to the court, deference to the trial judge supports the Act’s purpose of resolving claims in a just, speedy, inexpensive and simple way.
Reasoning and analysis
On trial fairness, the court relied on Jimenez v Azizbaigi and Garry v Pohlmann. Those cases recognize that small claims judges often must be more interventionist. They also hold that an appellate court should order a new trial where judicial conduct prevents or significantly interferes with a litigant’s ability to put their case before the court.
Having reviewed the transcript, the court described a challenging proceeding in which neither party was experienced in litigation. People frequently spoke at the same time, and both sides blurred the line between submissions and testimony. Ms. Rahmani had been told at the outset that her brother, as her support person, could not speak or lead evidence. He also could not observe as an assistant and then testify. The trial judge’s efforts were aimed at fairness for both parties, and the numerous interruptions were required to let the process continue effectively.
Mr. Rezaee Moghaddam referred to WhatsApp messages in his testimony but did not introduce them as exhibits. While the trial judge declined to review messages on Ms. Rahmani’s phone, nothing stopped her from testifying about their content. The court was therefore not persuaded that there was an imbalance in the opportunity to put records into evidence.
Turning to credibility, the trial judge had found Mr. Rezaee Moghaddam’s testimony simple, straightforward, clear, concise and consistent over time, and considered him an honest and reliable witness. Ms. Rahmani’s evidence about how much she and her brother paid, and when, was described as vague or unclear, inconsistent over time and improbable. The court saw no appearance of bias or application of stereotype. Even if it would have viewed credibility differently on the written record, it held that it could not interfere absent a palpable or overriding error or an error in principle.
As for the burden of proof, Mr. Rezaee Moghaddam had to prove on a balance of probabilities that an agreement existed, that the amount charged was consistent with it, and that a discernible unpaid balance remained. Ms. Rahmani carried the same standard for the facts she relied on, including deficiencies and payments beyond the final invoice. The trial judge had remarked on the difficulty of awarding the entire amount without good record keeping. Even so, on all the evidence she found an agreement for renovation work, no significant deficiencies proven, and amounts paid and owing as put forward by Mr. Rezaee Moghaddam. She rejected Ms. Rahmani’s account of additional undocumented cash payments as implausible or inconsistent. The court held that quantifying damages through testimony found credible was not a failure to apply the correct standard and did not amount to an error of law.
Ms. Rahmani also argued that the trial judge failed to account for evidence that Mr. Rezaee Moghaddam had removed her window blinds during the renovation and had not returned them. In her view, the replacement cost should have been set off against any amount owing. In the transcript, Mr. Rezaee Moghaddam testified only that he did not recall the issue or remember taking the blinds. The trial judge made no finding that he removed them, failed to restore them, or that any cost resulted. Her conclusion that these and other alleged deficiencies, including disputed damage to a gas line, did not justify withholding money owing for the renovation was left undisturbed, and no palpable and overriding error was established.
Ruling and overall outcome
The appeal was dismissed, leaving intact the Provincial Court’s award to Mr. Rezaee Moghaddam of the full $20,120.17 he claimed. He was also held entitled to costs at Scale B, but the decision does not quantify those costs, so no exact total can be determined.
Download documents
Appellant
Respondent
Other
Court
Supreme Court of British ColumbiaCase Number
S258645Practice Area
Construction lawAmount
Not specified/UnspecifiedWinner
RespondentTrial Start Date