Facts of the case
On January 19, 2012, a fire broke out in the right wheel area of a truck owned and operated by T & S Transportation Systems Inc. The truck was towing a trailer carrying a shipment of material from Toronto, Ontario to Vancouver, British Columbia, and the incident happened in Manitoba. T & S claimed that the defendants, Bendix Commercial Vehicle Systems LLC, Bendix CVS Canada Inc., Navistar Canada, Inc. and Navistar International Corporation, designed or manufactured the truck, and that its design and manufacture and/or its braking system were defective.
ICBC insured the truck and brought an action in Manitoba, while Intact insured the cargo and sued in Vancouver. To resolve the overlap, the two actions either had to be consolidated or the Vancouver action had to be amended to include the Manitoba allegations, and the parties ultimately chose amendment. Consolidation efforts, pleading amendments and examinations for discovery took the better part of a decade. A trial date was never set, although leave to set one was granted at a case planning conference on January 29, 2026.
On May 22, 2012, the truck was inspected by Dave Tyerman, an account manager with Bendix, and Al Grassing, a technical service manager with Navistar. A two-and-a-half-page memo in bullet form commenting on the inspection, with photographs attached, was signed by Tyerman, who wrote in it, “I am no certified inspector.”
At the recent examination for discovery of T & S’s vice president, Ms. Virk, the defendants learned that the truck had been scrapped or salvaged years earlier. Following its policy of destroying records after six years, T & S had also destroyed all records related to the truck, including maintenance records. As a result, it could not identify one of the two occupants of the truck at the time of the fire. Virk’s memory of the events and of the truck was extremely limited, and her inability to recall key facts was apparent from the discovery transcript.
Policy and legislative provisions at issue
Rule 22-7(7) of the Supreme Court Civil Rules allows the court, on a party’s application, to dismiss a proceeding if it appears that there is want of prosecution. The governing test comes from Giacomini Consulting Canada Inc. v The Owners, Strata Plan EPS 3173, 2023 BCCA 473, and has three parts: whether the plaintiff’s delay was inordinate, whether it was inexcusable, and, if both are established, whether the interests of justice still allow the action to proceed.
For spoliation, the Supreme Court of Canada in SS&C held at para 80 that the party alleging it must prove, on a balance of probabilities, that “(1) the evidence was intentionally destroyed, altered, mutilated, or concealed; (2) at the time of destruction, litigation was ongoing or reasonably contemplated; (3) the evidence was relevant to said litigation; and (4) it is reasonable to infer that the evidence was destroyed to affect the litigation.”
Reasoning and analysis
Relying on Wiegert v Rogers, 2019 BCCA 334, the court described inordinate delay as uncontrolled, immoderate, excessive and out of proportion to the matters in question, assessed holistically. A defendant has no obligation to advance an action, and its inactivity where no step was required of it is ultimately irrelevant, as noted in Tri-City Contracting Ltd. v Leko Precast Ltd., 2016 BCSC 623. Bendix and Navistar divided the delay into three tranches: consolidation, amendment of the notice of civil claim, and scheduling of discoveries, which together totalled roughly 12 years. They pointed to Krist v British Columbia, 2024 BCSC 1925, where the court stated that a delay of over four years in which nothing has occurred is inordinate. The court also cited Louie v Security National Insurance Company, 2025 BCSC 1315, for the principle that exchanges of correspondence generally do not count as steps in an action. Agreeing with the defendants, the court found multiple periods of excessive and uncontrolled delay that were within the plaintiff’s control and out of proportion to the matters in question.
Without a credible excuse, the natural inference is that inordinate delay is inexcusable. T & S argued it had made numerous attempts to reach agreement on consolidation, discovery scheduling and the pleading amendments. In the court’s view, however, the plaintiff drives a case like this one, and the more lawyers involved, the more vigilant it must be about delay. Cases sometimes have to be forced forward, for example by unilaterally scheduling dates that can be adjourned or rescheduled if they do not suit the defendants, because the onus to move the matter forward lies with the plaintiff. That effort was lacking here.
Once inordinate and inexcusable delay is shown, a rebuttable presumption of prejudice arises. Turning to the interests of justice, the court weighed factors including prejudice to the defendants, the length of the delay, the stage of the litigation, the context and reasons for the delay, the role of counsel, the public interest and the merits. Particularly relevant was that the truck, the single most important piece of evidence, no longer existed, its records had been destroyed, and no engineering evidence was ever obtained. According to the court, it was difficult to see how a design or manufacturing defect could be proven or defended in those circumstances.
T & S had signed a salvage agreement in 2012 authorizing ICBC to dispose of the truck, at a time when it knew of the incident but before the action began. It took no steps to preserve the truck, the trailer or the records. Tyerman’s memo offered some observations but was a far cry from an expert report. Truck parts requested at discovery, including the Bendix ATR-6 valve and other air brake components, no longer existed. Bendix and Navistar received no notice that the truck would be disposed of and never had the chance to conduct an expert forensic examination of it for the action. Under its operational policy, T & S also destroyed the truck’s maintenance records, driver logs and pre-trip inspection log within six years after it was aware of the incident and the litigation. Those records would have included mileage records and man hours, and the court found the failure to preserve them significant given that T & S was involved in litigation at the time.
On the alternative spoliation argument, the court found that both the truck and the records were intentionally destroyed, and that this happened when litigation could reasonably have been anticipated or had already started. Relevance was clear: the truck, the fleet records, the eyewitness’s identification and the maintenance records would all have mattered. On the fourth element, the court acknowledged that Virk, as vice president, followed company policy in destroying the records, but it declined to infer that this was done deliberately to affect the litigation. It characterized the destruction as an unfortunate event that was, at most, utterly thoughtless.
Ruling and overall outcome
Finding a substantial risk that a fair trial was no longer possible, the court held that the interests of justice favoured dismissal and dismissed the action under Rule 22-7(7). Spoliation was rejected as an independent basis for dismissal. Bendix and Navistar succeeded on the application and were awarded their costs of it, though the decision does not state any amount.
Download documents
Plaintiff
Defendant
Court
Supreme Court of British ColumbiaCase Number
S140356Practice Area
Civil litigationAmount
Not specified/UnspecifiedWinner
DefendantTrial Start Date