Facts of the case
Three related actions in the Superior Court of Quebec, District of Montréal, arise from redevelopment and renovation work on a building owned by the City of Montréal. The disputes involve extra work, extensions of the worksite and professional faults, among other issues. Côté Électrique (1994) inc. and Groupe LMT inc. each sued Construction Socam ltée and Compagnie d’assurance Trisura Garantie. Socam, in turn, is litigating against the City, which has brought warranty claims against an architecture firm and Les Services EXP inc.
Socam commissioned an expert report from LCO Consultants en construction et gestion inc., completed on February 25, 2026. The report continues an earlier expert report on delays in the performance of the work. It runs to 73 pages, with appendices exceeding 3,770 pages. The City applied to have numerous passages removed because they addressed questions for the trial judge or went beyond the expert’s mandate. Socam asked that the report remain intact to avoid distorting it, or alternatively that the expert be allowed to rewrite the problematic passages. The application was heard on October 13, 2026, and decided on October 21, 2026.
Legislative and contractual provisions at issue
Applications to reject an expert report are governed by article 241 of the Code of Civil Procedure. Under that article, a party may seek rejection of a report tainted by irregularity, serious error or partiality, provided it gives notice within 10 days of learning the ground. Under article 294, a party that misses this window is foreclosed from raising the issue at trial unless it could not have discovered the ground earlier despite its diligence.
A report found irregular may be corrected, redacted where this does not distort it, or rejected entirely. If it is rejected entirely, another expert report may be allowed. The expert’s fees may also be reduced or ordered reimbursed. Admissibility turns on four criteria drawn from R. v. Mohan: relevance, necessity, the absence of any other exclusionary rule, and a properly qualified expert.
LCO’s mandate was to assess the nature, justification, eligibility and reasonableness of the amounts Socam claimed. The report relied on contractual provisions, including clause 5.1.11 on change management and articles 5.1.11.3 and 5.1.11.4.1b) of the C.C.A.G. Drawing on them, it asserted that ODC 101 R1 was a valid contractual change for which Socam could legitimately claim compensation. A separate passage stated that the contractor’s right to indemnification was clearly established. The court did not interpret these provisions. It cited the passages as examples of legal conclusions falling outside an expert’s role.
Reasoning and analysis
The court described the application as a two-stage process: identifying the defect, then choosing the sanction. Probative value is generally not weighed at this stage. Two principles guide the exercise. Particularization requires a concrete analysis tied to the pleadings and the report. Prudence recognizes that the trial judge is sometimes better placed to rule on admissibility. The more flagrant the defect, the stronger the case for correcting or rejecting the report before trial.
Necessity was the criterion at issue. An expert report is necessary only if it supplies information likely to be outside a judge’s experience and knowledge. It is not necessary if it is merely helpful or if the expert tries to take the judge’s place. Domestic law generally does not meet this test, since the judge must take judicial notice of it. A report may still touch on legal questions, provided they are not the heart of the expert’s statements.
The court identified some 120 irregular passages and quoted several examples:
In the court’s view, the expert believed he could draw legal conclusions when his role was to explain the amounts claimed. The mandate was probably the source of the problem.
Socam argued that the case law had relaxed the rules in construction law. The court rejected this argument, noting that the earlier decisions concerned applications for total rejection and had dismissed them. Construction experts must take contracts, plans and specifications into account, and urban planners and accountants are in the same situation, but none may encroach on the judicial function. Setting a field-by-field threshold for legal conclusions would be inappropriate and has no legal basis.
The expert had crossed the line so often that intervention was required. Otherwise, the other parties could ask their experts to pronounce in the same manner, making the trial more cumbersome. The court also rejected Socam’s claim that removing the passages would completely distort the report. It found that the report would instead be centred on cost analysis. Rewriting was the less radical option because it lets the expert keep control of the report’s content while staying within the limits of expertise.
Ruling and overall outcome
The court granted the City of Montréal’s application in part. It ordered Socam to withdraw LCO’s report from the court record and to disclose an amended report to the other parties by December 18, 2026. The irregular passages identified in the City’s amended application must be rewritten so that they draw no legal conclusions on the value, eligibility, admissibility or merits of any item of Socam’s claim, or on the effect of a judgment. The expert may also simply remove them.
If no amended report is disclosed in time, Socam must redact every irregular passage and disclose the redacted report by January 8, 2027. If it fails to do so, Socam will be foreclosed from disclosing an expert report on the costs caused by the construction delays. The deadline to apply for setting the case down for trial and judgment was extended to January 29, 2027. No monetary amount was ordered, and legal costs are to follow.
Download documents
Plaintiff
Defendant
Other
Court
Court of QuebecCase Number
500-17-110848-192; 500-17-114466-207; 500-17-120161-222Practice Area
Civil litigationAmount
Not specified/UnspecifiedWinner
DefendantTrial Start Date