• CASES

    Search by

Côté Électrique (1994) inc. v. Construction Socam ltée

Executive Summary: Key Legal and Evidentiary Issues

  • The City of Montréal sought partial rejection of an expert report that LCO Consultants en construction et gestion inc. prepared for Construction Socam ltée, arguing that many passages addressed questions for the trial judge or exceeded the expert’s mandate.
     
  • At issue was the necessity criterion for admitting expert evidence, since domestic law is, in principle, for the judge alone to define and apply.
     
  • Roughly 120 irregular passages across a 73-page report and more than 3,770 pages of appendices expressed legal opinions, including on contractual entitlement and the effect of a Court of Québec judgment.
     
  • Socam’s reliance on earlier Superior Court decisions failed because those cases involved applications seeking total, not partial, rejection of expert reports.
     
  • Rewriting the irregular passages was preferred over outright removal, with mandatory redaction and possible foreclosure as the fallback.
     
  • Passages exceeding the expert’s mandate were few and tied to an earlier delay report, so the court left them in place.
     


Facts of the case

Three related actions in the Superior Court of Quebec, District of Montréal, arise from redevelopment and renovation work on a building owned by the City of Montréal. The disputes involve extra work, extensions of the worksite and professional faults, among other issues. Côté Électrique (1994) inc. and Groupe LMT inc. each sued Construction Socam ltée and Compagnie d’assurance Trisura Garantie. Socam, in turn, is litigating against the City, which has brought warranty claims against an architecture firm and Les Services EXP inc.

Socam commissioned an expert report from LCO Consultants en construction et gestion inc., completed on February 25, 2026. The report continues an earlier expert report on delays in the performance of the work. It runs to 73 pages, with appendices exceeding 3,770 pages. The City applied to have numerous passages removed because they addressed questions for the trial judge or went beyond the expert’s mandate. Socam asked that the report remain intact to avoid distorting it, or alternatively that the expert be allowed to rewrite the problematic passages. The application was heard on October 13, 2026, and decided on October 21, 2026.

Legislative and contractual provisions at issue

Applications to reject an expert report are governed by article 241 of the Code of Civil Procedure. Under that article, a party may seek rejection of a report tainted by irregularity, serious error or partiality, provided it gives notice within 10 days of learning the ground. Under article 294, a party that misses this window is foreclosed from raising the issue at trial unless it could not have discovered the ground earlier despite its diligence.

A report found irregular may be corrected, redacted where this does not distort it, or rejected entirely. If it is rejected entirely, another expert report may be allowed. The expert’s fees may also be reduced or ordered reimbursed. Admissibility turns on four criteria drawn from R. v. Mohan: relevance, necessity, the absence of any other exclusionary rule, and a properly qualified expert.

LCO’s mandate was to assess the nature, justification, eligibility and reasonableness of the amounts Socam claimed. The report relied on contractual provisions, including clause 5.1.11 on change management and articles 5.1.11.3 and 5.1.11.4.1b) of the C.C.A.G. Drawing on them, it asserted that ODC 101 R1 was a valid contractual change for which Socam could legitimately claim compensation. A separate passage stated that the contractor’s right to indemnification was clearly established. The court did not interpret these provisions. It cited the passages as examples of legal conclusions falling outside an expert’s role.

Reasoning and analysis

The court described the application as a two-stage process: identifying the defect, then choosing the sanction. Probative value is generally not weighed at this stage. Two principles guide the exercise. Particularization requires a concrete analysis tied to the pleadings and the report. Prudence recognizes that the trial judge is sometimes better placed to rule on admissibility. The more flagrant the defect, the stronger the case for correcting or rejecting the report before trial.

Necessity was the criterion at issue. An expert report is necessary only if it supplies information likely to be outside a judge’s experience and knowledge. It is not necessary if it is merely helpful or if the expert tries to take the judge’s place. Domestic law generally does not meet this test, since the judge must take judicial notice of it. A report may still touch on legal questions, provided they are not the heart of the expert’s statements.

The court identified some 120 irregular passages and quoted several examples:

  • that certain directives were valid authorizations and that the amounts assessed as eligible should be recognized;
  • that the absence of a fully formalized change order could not, in itself, invalidate the right to compensation for work performed and technically approved;
  • that a Court of Québec judgment confirmed Delorme’s entitlement to payment for extras authorized by Socam; and
  • that Socam’s payment obligation toward Pierre Delorme was legally confirmed, making its claim for those costs well-founded.

In the court’s view, the expert believed he could draw legal conclusions when his role was to explain the amounts claimed. The mandate was probably the source of the problem.

Socam argued that the case law had relaxed the rules in construction law. The court rejected this argument, noting that the earlier decisions concerned applications for total rejection and had dismissed them. Construction experts must take contracts, plans and specifications into account, and urban planners and accountants are in the same situation, but none may encroach on the judicial function. Setting a field-by-field threshold for legal conclusions would be inappropriate and has no legal basis.

The expert had crossed the line so often that intervention was required. Otherwise, the other parties could ask their experts to pronounce in the same manner, making the trial more cumbersome. The court also rejected Socam’s claim that removing the passages would completely distort the report. It found that the report would instead be centred on cost analysis. Rewriting was the less radical option because it lets the expert keep control of the report’s content while staying within the limits of expertise.

Ruling and overall outcome

The court granted the City of Montréal’s application in part. It ordered Socam to withdraw LCO’s report from the court record and to disclose an amended report to the other parties by December 18, 2026. The irregular passages identified in the City’s amended application must be rewritten so that they draw no legal conclusions on the value, eligibility, admissibility or merits of any item of Socam’s claim, or on the effect of a judgment. The expert may also simply remove them.

If no amended report is disclosed in time, Socam must redact every irregular passage and disclose the redacted report by January 8, 2027. If it fails to do so, Socam will be foreclosed from disclosing an expert report on the costs caused by the construction delays. The deadline to apply for setting the case down for trial and judgment was extended to January 29, 2027. No monetary amount was ordered, and legal costs are to follow.

Côté Électrique (1994) Inc.
Law Firm / Organization
Lalonde Geraghty Riendeau Avocats
Lawyer(s)

Vanessa Dupré

Construction Socam Ltée
Law Firm / Organization
Not specified
Lawyer(s)

Félix Brissette

Plaintiff
Compagnie d’Assurance Trisura Garantie
Law Firm / Organization
Not specified
Lawyer(s)

Félix Brissette

Ville de Montréal
Les Architectes Labonté Marcil S.E.N.C.
Law Firm / Organization
Casavant Bédard
Lawyer(s)

Antoine Bigenwald

Les Services Exp Inc.
Law Firm / Organization
Langlois avocats, s.e.n.c.r.l.
Court of Quebec
500-17-110848-192; 500-17-114466-207; 500-17-120161-222
Civil litigation
Not specified/Unspecified
Defendant