Facts of the case
Bourque Construction inc. runs an interior systems installation business. Under a subcontract entered into in October 2018, it provides services at the request of general contractor Construction Anjinnov inc. for the benefit of Anjinnov’s clients. Unpaid for the services rendered, Bourque claims $46,216.88 plus contractual interest from Anjinnov.
The parties had already litigated over the same sums under the same contract. In a dispute heard by the Superior Court in 2021, that court found that the subcontract’s payment clause created a condition depending on a future and uncertain event. It dismissed the claim as premature because the condition of payment by the clients had not yet been fulfilled. Since then, the clients have made an assignment of their property, which led Bourque to bring the present proceeding in the Court of Québec and Anjinnov to seek its summary dismissal.
Policy and legislative provisions at issue
The subcontract provides that payments will be made if and when the client has paid, and according to the amounts the client has paid. Anjinnov brought its motion solely under the second paragraph of article 168 of the Code of Civil Procedure, which allows a party to seek dismissal where a claim is unfounded in law even if the facts alleged may be true. At the hearing, its counsel confirmed he was not raising res judicata based on the earlier Superior Court judgment. In setting out Anjinnov’s argument that the condition had failed and the obligation no longer existed, the decision refers to article 1501 of the Civil Code of Québec and the Supreme Court of Canada’s decision in Ville de Sainte-Julie c. Investissement Laroda inc., 2025 CSC 44.
Reasoning and analysis
Anjinnov’s position was that the clients’ bankruptcy made it certain the condition of payment by the clients would not be fulfilled, so nothing was owed to Bourque. Bourque countered that nothing in the record showed Anjinnov receives no payment on the project, whether from the clients or from third parties such as another debtor, a trustee, a surety, an insurer or any other person. It also has no access to any accounting despite its requests. Bourque further alleged that Anjinnov had been negligent in following up on invoices and protecting the claim, including by failing to exercise its remedies in time, seek available securities and bonds, or take conservatory measures such as registering a legal construction hypothec.
The court noted that summary dismissal calls for caution and should be used sparingly and only in the clearest cases, citing Procureur général du Canada c. Confédération des syndicats nationaux, 2014 CSC 49, and Bohémier c. Barreau du Québec, 2012 QCCA 308. Whether Anjinnov received payments, and whether it was negligent in exercising its rights regarding the claim, were questions of fact requiring a complete evidentiary record that was not yet before the court. The clients’ bankruptcy was relevant, but the court could not conclude at this preliminary stage, without more evidence, that it necessarily caused the condition to fail and extinguished Anjinnov’s obligation.
Ruling and overall outcome
The court dismissed Anjinnov’s preliminary motion to dismiss Bourque’s amended originating application, with legal costs. It also ordered the court office to summon the parties to an upcoming provisional roll call in room 2.06 at 11:00 a.m. to schedule a 30-minute case management conference by videoconference. Bourque was the successful party on the motion, but no monetary amount was ordered in its favour, and the judgment does not quantify the legal costs. No ruling was made on the merits of its $46,216.88 claim.
Download documents
Plaintiff
Defendant
Court
Court of QuebecCase Number
500-22-295634-268Practice Area
Construction lawAmount
Not specified/UnspecifiedWinner
PlaintiffTrial Start Date