Soto Muni c. Performance R4L inc.

Executive Summary: Key Legal and Evidentiary Issues

  • The parties’ agreement to build a large dynamometer was characterized as a contract of service under article 2098 of the Civil Code of Québec.
     
  • Because no fixed price or estimate was ever agreed, the court valued the work on a quantum meruit basis and found the $12,686.40 unpaid balance justified.
     
  • R4L’s alleged $3,500 to $5,000 budget was never communicated to Mr. Soto Muni, and its competing $2,395 quote was set aside as unrealistic.
     
  • Defective-performance arguments were weakened by R4L’s failure to complain before receiving the invoice or to send a formal notice of default under articles 1594 and 1595 C.C.Q.
     
  • Video evidence filed by R4L could not establish poor workmanship without the help of an expert.
     
  • Only the $2,109.08 cost of successfully rebalancing the main roller was credited to R4L, while its $15,000 counterclaim failed for lack of supporting evidence.
     


Facts of the case

Performance R4L inc. (R4L) sells motorized equipment such as ATVs, side-by-sides and motorcycles, and also services and repairs these vehicles. In 2023, it owned a small mechanical dynamometer (dyno) that could only be used for motorcycles. R4L wanted a larger version for heavier equipment like side-by-sides, which are nearly the size of a car. Its managers knew Gerardo Soto Muni, who works in welding and machining, and asked him to build it.

No real plan was provided to Mr. Soto Muni beyond a rough sketch and a photo explaining the project. He told R4L his rate was $85 per hour plus the cost of necessary materials, and the parties agreed to proceed. R4L’s representative later claimed there had been a budget of $3,500 to $5,000, but that figure was never passed on to Mr. Soto Muni. Progress was discussed during the work, though amounts were never formally discussed.

The equipment was delivered in mid-March 2024, and the invoice was issued on April 3, 2024. It initially totalled $15,688.40, was later reduced to $14,186.40, and left an unpaid balance of $12,686.40. After receiving the reduced invoice, R4L still disputed owing the money and offered a far lower amount to settle, which Mr. Soto Muni refused; this was on June 21, 2024. Up to that point, R4L’s only complaint was a passing remark that the equipment was not functional because work remained to be done, and it never formally demanded that he correct or complete the job. R4L had one company attempt to balance the rollers at a cost of $1,971.82, and another rebalance the main roller at a cost of $2,109.08, which appears to have resolved the problem.

Mr. Soto Muni sued in the Small Claims Division of the Court of Québec for $12,686.40. R4L contested the amounts claimed, alleged poor workmanship, and counterclaimed $15,000 for damages it said it suffered because of his work.

Policy and legislative provisions at issue

The evidence of the contract’s terms was sparse, so the dispute turned on provisions of the Civil Code of Québec. Under articles 2803 and 2804, a party asserting a right must prove the supporting facts, and evidence making a fact more probable than not is sufficient. A contract of enterprise or for services is defined in article 2098 as one where a contractor or service provider undertakes to carry out material or intellectual work, or to provide a service, for a price the client agrees to pay. Article 1385 provides that a contract is formed by the mere exchange of consent between capable parties, unless the law or the parties require a particular form.

Article 2099 gives the contractor free choice of the means of performing the contract, with no relationship of subordination to the client, and article 2101 allows the contractor to bring in a third party while retaining direction of and responsibility for the work. Under article 2107, where the price was estimated when the contract was formed, the contractor must justify any increase, and the client pays it only to the extent it stems from unforeseeable work, services or expenses. Articles 1594 and 1595 govern putting a debtor in default, and require an extrajudicial demand to be in writing and to allow a sufficient time for performance.

Reasoning and analysis

The court classified the arrangement as a contract of service formed by the parties’ exchange of consent. Though a written contract was not required, the court noted that one makes interpretation easier, and that evidence of the contract’s content here was sparse. It also acknowledged having no judicial knowledge of how such equipment is built, and found that the evidence did not show what manufacturing methods should have been used. As contractor, Mr. Soto Muni was free to choose his methods and to subcontract part of the work.

There was neither a fixed price nor an estimate. Relying on Professor Vincent Karim’s text on contracts of enterprise, the court explained that a client who fails to request an estimate before contracting must bear the consequences, with the price set on a quantum meruit basis and the risks borne by the client under article 2106. In practical terms, the judge must determine what the work is worth.

Mr. Soto Muni paid for bearings and housings, the fabrication of a small and a large roller, steel, steel bars, steel tubes, other steel materials and assorted hardware, and he also subcontracted some of the work. According to his invoice, these purchases totalled $7,561.32, and adding his labour time produced the $12,686.40 balance claimed. Nothing in the invoice suggested the amounts were unreasonable. No budget had ever been raised with or accepted by Mr. Soto Muni. R4L filed a quote of $2,395 plus taxes for the same work, but the court rejected it as unrealistic given the material costs alone, describing it as either an accommodation document or a quote for work that was not identical. The full $12,686.40 was therefore found justified.

On the quality of the work, the court stressed that the dyno still had to function for its intended use. R4L, however, had not complained before receiving the invoice, even though the equipment had been delivered weeks earlier, and during settlement talks it only said the equipment was not functional. It never reported a problem or put Mr. Soto Muni in default under articles 1594 and 1595, which led the court to question how serious the problems were. A video filed by R4L did not help, since the court could not assess workmanship from a video without an expert.

Mr. Soto Muni admitted that some adjustments were still needed, but he refused to make them until he was paid, while R4L refused to pay. R4L brought in two companies to adjust the equipment. The first company’s $1,971.82 attempt to balance the roller was unsuccessful, and the court held that Mr. Soto Muni did not have to bear that cost. R4L was, however, entitled to a credit for the $2,109.08 paid to the second company, whose work balancing the roller completed the job. R4L’s counterclaim was unsupported by any document or other evidence justifying the amounts sought.

Ruling and overall outcome

The court allowed Mr. Soto Muni’s claim in part and ordered Performance R4L inc. to pay him $10,714.54, with interest and the additional indemnity under article 1619 C.C.Q. from May 8, 2025, plus legal costs. R4L’s $15,000 counterclaim was dismissed without legal costs.

Gerardo Soto Muni
Law Firm / Organization
Not specified
Performance R4L Inc.
Law Firm / Organization
Not specified
Court of Quebec
755-32-702114-259
Civil litigation
$ 10,715
Plaintiff