9322-0481 Québec inc. (LB Gitech) v. Bouzo

Executive Summary: Key Legal and Evidentiary Issues

  • Both parties treated the $70,000 renovation contract as fixed-price, and the court rejected two additional invoices for lack of agreement on their cost or on delay penalties.
     
  • Cash-only payments left the homeowner unable to prove he paid more than the $58,560 the contractor acknowledged.
     
  • Five admitted unfinished items reduced the contract balance, with the court setting values where neither party offered calculations.
     
  • Recovery of corrective-work costs under article 1602 of the Civil Code of Québec depended on a prior formal demand, limiting compensation to the defects actually reported.
     
  • No probative value was given to the contractor’s expert evidence, while the homeowner’s expert filed a very detailed report.
     
  • Stress and inconvenience damages of $25,000 were refused because no delays were calculated and the homeowner did not show anything beyond the inconvenience normal to a renovation.
     


Facts of the case

In October 2021, Yann Joseph Bouzo hired 9322-0481 Québec inc., which does business as LB Gitech, to renovate his residence for $70,000. Gilles Elbez, who described himself as one of the company’s directors, drafted the one-page contract, directed and took part in the work, and prepared the invoices. During the project, an act of vandalism flooded the basement. A wall slated for removal also turned out to be load-bearing, so Mr. Bouzo had to bring in professionals and then a third-party company to take it out.

In June 2022, LB Gitech issued four invoices totalling $122,600 before taxes and acknowledged receiving $58,560. It sued for $64,040 plus interest at 18% per year. Mr. Bouzo argued that some work was deficient, some was never done, the additional invoices were unjustified, and no interest rate had been agreed. By counterclaim, he sought $57,792.18 to correct poor workmanship and $25,000 for stress and inconvenience. The Court of Québec heard the matter on April 29 and 30, 2026.

Policy and legislative provisions at issue

Both parties treated the agreement as a fixed-price contract under articles 2098 and 2109 of the Civil Code of Québec. Under that rule, the price stays the same even if the conditions of performance change, unless the parties agree otherwise. The contract set the price at $70,000 and priced several items by the day at $55 per hour. These included three days for the installation of three items, among them electrical work for ceiling Bluetooth speakers, and ten days ($4,400) for an under-stairs closet with two doors and a washing machine. Seven days ($3,080) were allotted for polyurethane insulation of the room under the stairs and floor repair, 12 days ($5,280) for complete plastering and painting and the repair of two brick walls, and one day ($440) for a garage shelf. No conventional interest rate was stated. The contract estimated the project at about three months, holiday period included, on the assumption that the wall to be removed was not load-bearing.

Article 2100 requires a contractor to act in the client’s best interests with prudence and diligence, follow the usual practices and rules of the trade, and deliver work that conforms to the contract. To have work performed by a third party at the contractor’s expense under article 1602, the client must first put the contractor in default through an extrajudicial or judicial demand. The court also referred to article 2803, paragraph 2, on the question of payment, and to article 235 of the Code of Civil Procedure regarding the expert’s declaration that accompanies a report.

Reasoning and analysis

LB Gitech’s $64,040 claim did not reconcile with the evidence. Although the invoices showed taxes, the company left them out of its accounting and its claim. Mr. Elbez also said he was not seeking payment of invoice 173980, which was absent from the company’s demand letter as well. As for invoice 173978, covering $20,640 in additional work before taxes, the court rejected it because it was not broken down and there had been no meeting of the minds on cost; Mr. Elbez testified that he prepared it only because Mr. Bouzo refused to pay the balance on the main invoice. Invoice 173979, a $14,400 penalty for having to move the work repeatedly, duplicated a $0.00 entry on invoice 173978, and Mr. Elbez conceded there was no agreement on delay penalties, so it too was dismissed.

On the main contract invoice, Mr. Bouzo said he had paid $63,060 rather than $58,560, but all payments were made in cash and, apart from a few notes, no proof of payment was offered. A contract balance of $11,440 was therefore established. LB Gitech admitted that five contract items were never completed but offered no figures. Mr. Bouzo, meanwhile, sought both a price reduction and the cost to complete the same work, which the court said would compensate him twice. Drawing on the contract’s daily rates and the limited evidence, the court deducted $440 for the Bluetooth speakers and $350 for the laundry room doors, the latter based on an IBuild estimate Mr. Bouzo filed. It also took off $1,500 for the unfinished flooring under the stairs, $1,000 for the brickwork around two wall-mounted air conditioners, and $440 for the garage shelf, leaving $7,710 owing. With no agreed rate in the contract, interest runs at the legal rate rather than 18%.

Turning to the defects, the court held that a homeowner seeking corrective work at the contractor’s expense must first send a formal demand. That demand must specify the failures, invite the contractor to perform, and announce the consequence of not doing so. The court relied on the treatise by Baudouin and Jobin and on Béton St-Pierre inc. c. Lampron, 2013 QCCS 1099. The required elements appeared across Mr. Bouzo’s August 12, 2022 letter, his lawyer’s April 12, 2023 letter and his amended counterclaim, but only the five deficiencies listed in his own letter could be compensated. Mr. Bouzo’s expert, general contractor and building inspector Gabriel Boucher, filed a detailed, photo-supported report and testified in a precise and structured way. LB Gitech’s expert, Ronen Tadmor, produced an extremely brief report without the expert’s declaration and held no competency cards. An acquaintance whom Mr. Elbez had consulted, he commented on a second floor he never visited based on Mr. Elbez’s description. Because he repeated what Mr. Elbez told him, the court found a lack of objectivity. His testimony and report were given no probative value.

Claims about the garage ceiling and the glue-stained basement parquet failed for lack of evidence. On the roughly ten cracked tiles on the heated floor of the living room, kitchen and dining room, the only cost estimate called for removing all ceramic, heating cables and membrane across the entire ground floor, and its author did not testify. Finding nothing to support work on that scale, the court set the repair at $2,000. For the master bathroom, a $6,050 estimate proposed demolishing and rebuilding every surface, but the evidence on the need for all of that work was thin, so $2,500 was awarded. Mr. Bouzo’s complaint about generally unprofessional finishing was too vague for LB Gitech to understand its nature and was dismissed. That brought the defect award to $4,500.

The $25,000 stress claim also failed. Mr. Bouzo testified that he expected the work to end in February 2022, that it finished on May 22, 2022, and that he had to live in the residence during the renovations with his spouse and three children. No delay calculation or start date was put in evidence, and the delays tied to the load-bearing wall were not attributable to LB Gitech. Mr. Bouzo had also requested additional work himself, including heated floors throughout the ground floor and work required after the vandalism. He had not shown how his situation went beyond the inconvenience normally inherent in a major renovation.

Ruling and overall outcome

After setting off the $4,500 awarded to Mr. Bouzo against the $7,710 balance owed under the contract, the court ordered Mr. Bouzo to pay LB Gitech $3,210. That amount carries interest at the legal rate and the additional indemnity under article 1619 of the Civil Code of Québec from August 24, 2022. LB Gitech thus prevailed in part, recovering $3,210 of the $64,040 it had claimed, while Mr. Bouzo’s stress and inconvenience claim was dismissed. Because both the claim and the counterclaim were partially granted, no legal costs were awarded and each party bears its own.

9322-0481 Québec Inc. (doing business as LB Gitech)
Law Firm / Organization
Not specified
Yann Joseph Bouzo
Law Firm / Organization
Not specified
Lawyer(s)

Elisabeth Ouaknine

Court of Quebec
500-22-275691-221
Construction law
$ 3,210
Other