Facts of the case
7852517 Canada inc. owns a building at 2251 Letourneux Avenue that it leased in full to Dental Wings inc. In 2012, it bought the neighbouring building at 4325-4347 de Rouen Street in Montreal. The owner and Dental Wings later agreed to extend the building by means of that adjacent property. A new lease signed on May 16, 2018, covering the entire building, was to begin on July 1, 2019, at a monthly rent of $56,904.17 plus taxes.
On December 18, 2018, the owner hired Les Entrepreneurs généraux Lambda inc. under a turnkey CCDC contract. The contract had a lump-sum price of $2,300,000 and covered connecting the renovated adjacent building to the existing one. Lambda subcontracted the welding to Métaux T.R.D.M. inc. On May 9, 2019, while Métaux T.R.D.M. was carrying out welding work, a fire broke out in the attic of the existing building and in the extension under construction. It rendered both the existing building and the nearly completed adjacent building entirely unusable, and the June 30, 2019 completion date was postponed. The decision puts the owner's rental loss from May 9, 2019 to March 12, 2020 at $1,225,681, taxes included.
The owner sued Lambda for damages in September 2019. That same month, Toitures & Construction Robitaille, one of Lambda's subcontractors, registered a legal construction hypothec against the building. Lambda neglected to have the hypothec struck off, which forced the owner to defend the hypothecary action and pay legal fees to have the registration removed. On March 1, 2020, architect Maxime Duquette issued a certificate of substantial completion for Lambda's work and accepted the work with reservations. Doyle Rénovation completed the reconstruction on March 12, 2020; according to an exhibit cited in the decision, it had replaced Lambda as general contractor as of January 1, 2020.
The parties settled the 2019 damages action on December 19, 2022. Under the settlement, the owner received $575,000 as a rent indemnity. The settlement carved out a separate, not-yet-filed claim by Lambda for an alleged $117,738.93 in contractual holdback, credits and/or extras, which the owner denied owing. Lambda sued on August 25, 2023, claiming $122,675.08 in unpaid extension and reconstruction work. The owner argued the claim was prescribed. It also counterclaimed for $650,681 in damages and lost rental income, but limited that counterclaim to whatever amount it might be ordered to pay Lambda.
Policy and legislative provisions at issue
Article 8.6 of the 2018 Dental Wings lease suspended the tenant's obligation to pay rent while the premises were unavailable due to force majeure, and the owner's claimed rental losses were tied to that clause. Under clause 2.4.3 of the CCDC contract, the owner could deduct the value of corrective work from the contract price. The owner pointed out that Lambda never contested the certificate of substantial completion, either under article 5.4 of the contract or informally. Absent an agreement to the contrary, clause 9.1.3 left Lambda responsible under the contract for repairs following the loss. Paragraphs 7 to 9 of the 2022 settlement preserved both parties' rights and legal arguments on Lambda's carved-out claim.
On the legislative side, article 2925 of the Civil Code of Québec sets a three-year prescription period for contractual liability claims. Under article 2111, a client need not pay before accepting the work, and article 2116 starts prescription between contractor and client at the end of the work. Article 2110 defines that point as the moment the work has been produced and is ready for its intended use. Filing a judicial application interrupts prescription under article 2892. The owner also invoked article 2803 in arguing that Lambda had not met its burden of proof. For the prescription calculation, the court added 170 days of suspension under the government's COVID decree, citing two ministerial orders issued in 2020.
Reasoning and analysis
Prescription between a contractor and its client runs from the end of the work, which occurs once the work can serve its intended purpose, even if minor corrections remain. The court relied on the architect's certificate, which set March 1, 2020 as the end of the work. No witness contradicted that date, and the heading of the certificate's list of completion, correction or repair work showed the architect was inventorying residual work and minor deficiencies. Cross-examination of Lambda's representative, Steve Savvas, established that the listed items were essentially minor. A February 5, 2020 deficiency list from Grenier expert-conseil pointed the same way, and the court found Savvas's evidence that some items were significant vague and unconvincing.
The owner's representative, Naoum Araj, visited the site twice a week. He testified that Lambda left in December 2019 and never returned, leaving the owner to finish the floors, the roof connection, the drywall and the baseboards. Two further pieces of evidence supported the March 1, 2020 date: an electrical warranty certificate dated that day, and the expiry of Lambda's builder's risk insurance on January 31, 2020. With the 170-day suspension added to the three-year period, Lambda had until August 19, 2023 to sue, so its claim was prescribed.
The court went on to address the merits and found that both parts of Lambda's claim would have failed anyway. On the $46,911.62 contract balance, the court agreed with the owner on two points. First, Lambda's calculation relied on an erroneous tax computation that inflated the contract price by $20,000. Second, it ignored the value of defective and unexecuted work, even though clause 2.4.3 allowed the owner to deduct corrective costs. Araj's account of the defects and unfinished work was found credible, but the parties had never agreed on the resulting credits or referred the question to the consultants. Savvas's testimony was described as imprecise, inconclusive and full of contradictions.
On the $75,763.46 insurance-work claim, Lambda sought the taxes on an invoice for which, according to Lambda, the owner had paid only the pre-tax amount of $305,532.54 after being indemnified by its insurer. Lambda also claimed a further unpaid amount and taxes on a second invoice. It made three arguments: that the owner had agreed to pay it half of the insurance claim, that the owner had claimed input tax credits, and that the partial payment amounted to an acknowledgment of the whole debt. The court found no evidence of any written or verbal agreement obliging the owner to pay more than it received from its insurer. It accepted Araj's testimony that the insurer did not cover the taxes.
As for the counterclaim, the owner had expressly capped it at the amount needed to extinguish any debt it might owe Lambda. The court reconfirmed that limit with the owner at the hearing.
Ruling and overall outcome
The court dismissed Lambda's originating application in its entirety. It also took note that the owner's counterclaim stood at $0 and had become moot. 7852517 Canada inc. prevailed, and the court awarded it legal costs. No amount was ordered in its favour beyond those costs, and the judgment does not quantify them.