Facts of the case
Société d'assurance Beneva inc. insures a home in Lévis owned by Marie-Josée Haley and Benoît Lemay. In June 2011, the owners hired Magasins Trévi inc. for the purchase and installation of an in-ground pool in their backyard. On April 13, 2021, they discovered significant cracks in the pool walkways. They immediately notified Trévi and filed a claim with Beneva.
In 2024, Haley and Lemay sued Beneva, Trévi, Charles Nadeau (Terrassement Québec enr.) and Les Constructions Maurice Bilodeau for insurance indemnity and damages. Beneva settled with its insureds on October 8, 2025 for $100,000 in exchange for a release and conventional subrogation, and continued the proceeding on December 10, 2025. An amended case protocol, acknowledged by the court on February 20, 2026, required Beneva to file its expert report on the cause of the damage by April 24, 2026. Engineer Jean-Daniel Lemay of CEP Forensique did not complete the report until August 24, 2026. Trévi contested its filing, and Beneva applied for leave to file it late and for a third extension of the deadline to set the case down for trial and judgment.
Policy and legislative provisions at issue
The decision does not address any insurance policy wording. Instead, the application turned on three articles of Quebec's Code of Civil Procedure. Article 150 makes a court-accepted case protocol binding on the parties, who may face legal costs for failing to comply. Under article 232, parties are limited to one expert report per discipline unless the court authorizes more because of the complexity or importance of the case or developments in the field. Article 293 provides that an expert's report stands in for testimony and must be filed within the prescribed time limits, but it may be received after those limits with the court's permission. The court also relied on Court of Appeal authority holding that, although parties must comply with a case protocol in good faith, it is neither a straitjacket nor an absolute bar to steps it does not provide for.
Reasoning and analysis
On necessity, the court found that the report was the only expert evidence supporting Beneva's position that construction or workmanship defects caused the damage. The engineer concluded that the damage resulted from inadequate preparation and insufficient compaction of the backfill under the pool and walkway. In his view, improperly positioned mesh under the walkway concrete greatly aggravated the extent of the cracks. His report also answered Trévi's defence that drain-related washout of the backfill was to blame. He noted that excavation photographs showed no sign of washout and that no worsening of the damage was observed between 2021 and 2026, despite the absence of corrective work during that period.
Turning to the delay, the court noted that engineer Olivier Biron had originally handled the file. His investigation form and supplementary investigation could not serve as an expert report for the court. After he left CEP Forensique, steps were taken to confirm whether Lemay, who had been responsible for the review, could take over the mandate and finalize the report. Beneva, like Trévi, pressed the insureds to tell it when corrective drain work or a backyard redevelopment began, since the experts would foreseeably want to revisit the site. Haley informed Beneva's lawyer on May 14, 2026 that work had started, but he did not pass this on to Trévi's counsel or to the engineer. Around July 12, 2026, Haley sent him photographs that he was unable to open. Beneva obtained the full set on July 21, 2026 and forwarded them to the engineer and Trévi that same day.
The court attributed the delay to the insureds' slowness with undertakings, their failure to inform Beneva in advance of the start of the work, and the summer vacation of Beneva's lawyer. It found that the lawyer, through inadvertence, did not show great diligence at that moment. Even so, the court remained convinced of his good intentions, since Beneva's own engineer was also unable to access the site.
Trévi was not taken by surprise, the court held, because the expert report appeared in the amended protocol and in earlier versions. Trévi had been promptly informed of the findings and preliminary conclusions issued by CEP on March 9, 2022 and by Origin. Its engineer, Radu Ene, inspected the site on June 29 and 30, 2023, and two other Trévi representatives visited on June 20, 2022. Several photographs taken from different angles during the May 2026 work showed the uncovered drains and offered an acceptable alternative to a site visit. Trévi could also examine the contractor retained by the insureds and contest the report's probative force at the hearing on the merits.
On procedural conduct, the insureds' negligence could not be imputed to Beneva, since they were third parties over whom it had no power. The court described Beneva's own efforts to be kept informed as beyond reproach. Its lawyer's failure to alert the engineer and Trévi on May 14, 2026 was found not very judicious, but not enough to leave Beneva without any expert evidence. At this stage, nothing allowed an inference that the lack of notice was meant to conceal evidence or influence the litigation. Allowing both sides to present technical evidence served the search for truth and was more reasonable than rejecting the report.
Ruling and overall outcome
Beneva's application was granted. The court relieved Beneva of its default under the protocol and authorized it to file the August 24, 2026 investigation report within five days. It also extended the deadline to set the case down for trial and judgment to May 14, 2027, giving Trévi time to retain its own expert and the parties time to complete the remaining steps. The parties were exempted from preparing a new case protocol. No monetary amount was ordered in Beneva's favour, and legal costs were left to follow.
Download documents
Plaintiff
Defendant
Court
Quebec Superior CourtCase Number
200-17-035998-244Practice Area
Civil litigationAmount
Not specified/UnspecifiedWinner
PlaintiffTrial Start Date