Couvre-Planchers Dimension (2022) inc. v. Sajo inc.

Executive Summary: Key Legal and Evidentiary Issues

  • The buyer of a flooring subcontractor's receivables, acquired after the subcontractor filed a notice of intention to make a proposal, sued the contractor for $188,918.08.
     
  • Evidence showed the parties had agreed the work was 21% complete when the contract ended, valuing it at $76,055.97.
     
  • Materials worth $40,639.82 were excluded because the contractor had paid the supplier, Gerflor, directly.
     
  • Legal compensation failed because the contractor's alleged damages arose after the proposal was filed and were not certain, liquid and exigible at that time.
     
  • Without a cross-application, the contractor could not obtain judicial compensation.
     
  • An abuse-of-procedure application was dismissed since the action itself was well founded and a trial was needed to weigh the evidence.
     


Facts of the case

Sajo inc. was the contractor responsible for the renovation of an eight-storey university pavilion in Montreal, a project worth more than $38 million that ran from 2021 to 2024. In April 2021 it retained Tapis Dimension inc. as a subcontractor to supply and install floor-covering materials, under a $315,000 contract that resulted from a call for tenders. In summer 2022, Tapis Dimension invoiced its work at $188,918.08. It had completed two of the eight floors but had not been paid by Sajo.

On August 8, 2022, Tapis Dimension filed a notice of intention to make a proposal, and on August 16 it told Sajo it consequently had to stop work. A registrar of the Superior Court then approved, on October 20, 2022, a transaction and purchase agreement under which Couvre-Planchers Dimension (2022) inc. acquired all of Tapis Dimension's rights, title and interest in its assets, including accounts receivable. Sajo received formal notice of the assignment, which was also published in Quebec's Register of Personal and Movable Real Rights, making it effective against all.

Couvre-Planchers Dimension sued Sajo for $188,918.08. Sajo argued it owed nothing, because the damages it suffered when Tapis Dimension left the site at an inopportune time exceeded the claim and should be set off through compensation. It also asked the court to declare the claim abusive. The buyer answered that the amount reflected the receivable assigned to it and pointed to two earlier judgments it had won against other debtors of Tapis Dimension on receivables from the same assignment.

Policy and legislative provisions at issue

No clause of the subcontract is quoted in the decision. The analysis rests on the Civil Code of Québec, the Bankruptcy and Insolvency Act and the Code of Civil Procedure.

Under articles 2125, 2126 and 2129 C.C.Q., the parties to a contract of enterprise or for services may resiliate it unilaterally without proving fault. A service provider, however, needs a serious reason, cannot end the contract at an inopportune time, and must do what is necessary to prevent loss to the client. A provider that fails to meet these criteria is at fault and owes the proven damages directly tied to the termination. The court also noted that such a contract is characterized as a relative fixed-price contract where the client reserves the right to modify the work and its conditions of performance and the contract sets out modification procedures.

Articles 1672 and 1673 C.C.Q. govern compensation between parties who are reciprocally debtor and creditor. Legal compensation operates by law between coexisting debts that are certain, liquid, exigible and fungible, while judicial compensation must be sought through a cross-application so the debt can be liquidated. Citing sections 97(3), 101.1 and 121 of the Bankruptcy and Insolvency Act, the court stated that in a bankruptcy or proposal, compensation is possible between debts existing on or before the filing date, but not where one of the debts arises afterward. Articles 51 and 53 C.C.P. allow an abusive application or pleading to be dismissed. Where the abuse reveals wrongful conduct, article 54 C.C.P. allows damages to be ordered. The court stressed that the threshold for a finding of abuse is high.

Reasoning and analysis

The court first rejected the $188,918.08 figure. Both sides agreed the work was 21% complete when the contract ended in August 2022, which the court valued at $76,055.97, and Sajo had clearly said it would pay that share. It was not paying at that point because it was waiting for releases showing that Tapis Dimension's own subcontractors had been paid.

Materials were then removed from the valuation. Emails and attachments showed that, when work stopped, Tapis Dimension asked Sajo to pay the supplier Gerflor directly so the site could continue, and the evidence established that Sajo did so. Those materials were worth $40,639.82 according to the invoices. Couvre-Planchers Dimension failed to prove that Tapis Dimension had used any other materials: its invoices were not broken down, and its witnesses had no personal knowledge of the site operations or of the invoice details.

The buyer did, however, prove partial performance worth $35,686.15. Tapis Dimension had finished two of eight floors, or 21% of the contract, a point no one disputed, and the quality of its work was not challenged. Its June and July 2022 invoices came to $35,686.15 once materials were excluded, and the court held that Sajo had to pay for work that benefited it alone.

Sajo's compensation defence failed on both routes. Legal compensation was unavailable because the notice of proposal and the work stoppage both occurred in August 2022. Sajo's damages claim stemmed from harm that came afterward, so it was not certain, liquid and exigible when the proposal was filed. Judicial compensation was also out of reach, as Sajo had not filed a cross-application, without which its claim could not be liquidated.

On abuse of procedure, the court explained that the concept targets a judicial application or a pleading, not individual arguments. The action itself was well founded, since the buyer was entitled to $35,686.15. By contrast, the $188,918.08 figure had no chance of success. Although it found some support as the receivable vested through the assignment, it was contradicted by the parties' agreement modifying and setting the value of the work at $76,055.97. Even so, a trial was required to decide between the competing versions on the evidence, so the action could not be called abusive.

Ruling and overall outcome

The Superior Court allowed the claim in part and ordered Sajo inc. to pay Couvre-Planchers Dimension (2022) inc. $35,686.15, with interest at the legal rate from October 26, 2023 and the additional indemnity under article 1619 C.C.Q. Sajo's abuse-of-procedure application was dismissed, and legal costs went to Couvre-Planchers Dimension (2022) inc. The decision does not quantify the interest, additional indemnity or costs.

Couvre-Planchers Dimension (2022) Inc.
Law Firm / Organization
De Louya Markakis Avocats
Lawyer(s)

Louis Karkaselis

Sajo Inc.
Law Firm / Organization
De Grandpré Chait S.E.N.C.R.L.
Quebec Superior Court
500-17-128682-245
Construction law
$ 35,686
Plaintiff