In November 2015, Chandos Construction Ltd. entered into a fixed-price agreement with the Municipal District of Greenview No. 16 to build a new water treatment plant and upgrade existing water infrastructure. Associated Engineering Alberta Ltd. designed and administered the project for the Municipal District. Chandos began work in January 2016, and the agreement contemplated completion by March 2017. The project ran well behind schedule, and Chandos did not issue its final certificate of substantial performance until September 26, 2018.
Between May 15, 2016 and June 12, 2018, Chandos sent 16 notice letters to the appellants. Fourteen gave notice of delay or potential impact relating to site access, site changes, design issues, the condition of existing infrastructure, and a lack of direction or response. Many stated that Chandos was incurring costs, but none claimed payment. The other two, dated September 7, 2017 and November 11, 2017, were captioned "Notice of Dispute" and concerned work Chandos said fell outside the contract's scope.
On December 24, 2018, Chandos asked Associated Engineering for a 17-month extension of the contract time and a $1,487,807 increase in the contract price on account of delay. Associated Engineering responded on March 14, 2019, stating that Chandos had already been compensated for 109 days of delay affecting the project's critical path and that the remaining delays were not compensable, while inviting further detail. The contract was later purportedly terminated in 2020.
Chandos sued on September 24, 2020, claiming $1,487,807 for delay and $1,200,000 for additional work, a total of $2,687,807. It alleged the Municipal District was liable in contract and tort, and Associated Engineering in tort. On November 17, 2020, Chandos amended its claim to add $311,044.91 for work performed under the agreement for the period ending June 30, 2020. The appellants applied for summary dismissal under Rule 7.2(a), first of the delay claim only, and later expanded the application to cover the additional work claim, excluding the $311,044.91. They relied on the pleadings and on Mr. Baker's affidavit and questioning. An applications judge denied the application on November 3, 2023, and a chambers judge dismissed the appeal from that decision.
Policy and legislative provisions at issue
Section 3(1)(a) of the Limitations Act, RSA 2000, c L-12, gives a defendant immunity from liability if the claimant does not seek a remedial order within two years after it first knew, or ought to have known, that the injury had occurred, was attributable to the defendant's conduct, and, assuming liability, "warrants bringing a proceeding." Because Ministerial Order 27/2020 suspended running limitation periods for 75 days during the COVID-19 pandemic, the relevant period was two years and 75 days, meaning the claims were out of time if Chandos had the required knowledge before July 11, 2018. "Injury" includes economic loss under section 1(e), and section 7(1) allows parties to agree to extend the limitation period.
Rule 7.2(a) of the Rules of Court allows the court to grant judgment where "admissions of fact are made in a pleading or otherwise."
The construction agreement required notice of a delay claim to the engineer "within five (5) Business Days after the occurrence of the event which has caused the delay" (GC 47.2). Under GC 47.6, failing to give "separate express Notice in strict compliance with GC 47" barred the contractor from claiming any adjustment to the contract price for that delay. GC 58.1 required a contractor intending to claim a price increase to give "timely Notice in writing of intent to Claim." GC 59.3 provided that the mandatory dispute resolution provisions did not prevent legal action where "necessary to... preserve a right... that would otherwise be barred by statute." The dissent also considered GC 14.5 (prompt written notice of foreseen delay), GC 53.2 (no change without a written change order or change directive), and GC 57.5 (immediate notice of claims arising from concealed or unknown conditions).
Reasoning and analysis
Both the majority and the dissent agreed that the chambers judge applied the wrong test for summary dismissal. The majority held that the general summary judgment principles from Hryniak v Mauldin and Weir-Jones Technical Services Incorporated v Purolator Courier Ltd apply equally to applications under Rule 7.2(a). Summary judgment is not limited to the "clearest of cases," and a disposition need not be "plain, unambiguous, or unequivocal" to be fair. Limitations defences receive no special treatment. Since the chambers judge made no factual findings on the limitations issue, the majority reviewed the record and decided that issue afresh. Having found the claims time-barred, it declined to decide whether the contract's notice provisions also barred them.
The majority found no genuine issue about Chandos's awareness of the appellants' alleged conduct before July 11, 2018. The statement of claim alleged that Chandos discovered the deteriorated condition of the existing facilities in January 2016, and the causes of its other claims were set out in the notice letters. Mr. Baker admitted those letters were issued because Chandos viewed the events as attributable to the appellants. The additional work had been performed in 2016 and 2017, and most of the delay was incurred, or had begun, well before July 11, 2018.
Chandos raised three main responses, and the majority rejected each. Its argument that it could not quantify its costs until the project ended failed because the quantum of a claim need not be crystallized for a limitation period to run. Mr. Baker's admissions showed that Chandos tracked its costs and delays during the work and was aware at the time of each notice letter of more than a trivial cost or impact. Its second argument, that it would have had to start 16 separate lawsuits, was found to be without merit: a single statement of claim filed by early 2018 could have captured all the additional work claims and most delay claims, with the remaining 2018 delay claims added by amendment before the service deadline in early 2019. The parties also did not agree to extend the limitation period.
On appeal, Chandos's main argument was that it suffered no injury until the appellants refused to pay in March 2019. The majority found this position untenable because it would let a claimant both delay and control the running of a limitation period, undermining the certainty, evidentiary, and diligence rationales behind limitations law. It acknowledged that a refusal to pay can trigger a limitation period where a service provider performs agreed work and is not paid, but that was not the conduct alleged here. Chandos's claims rested on improper design, improper administration, inadequate site access, and forced additional work, all of which occurred before the costs were incurred. Negotiations after the December 2018 claim letter did not postpone the limitation period either. Ontario and Saskatchewan courts have recognized that an alternative claims process may delay a limitation period. However, in Saskatchewan (Highways and Infrastructure) v Venture Construction Inc, the Saskatchewan Court of Appeal held that the contractor must at minimum invoke that process and satisfy its requirements, including notice. Mr. Baker acknowledged that Chandos sought no extension or price adjustment in its notice letters and requested no compensation until it achieved substantial performance.
The majority concluded that before July 11, 2018, Chandos knew of the allegedly wrongful conduct and that the resulting cost impact far exceeded any trivial, minimal, or speculative amount, so a proceeding was warranted. A suggestion that construction-specific policy arguments or evidence might be raised later could not defeat summary dismissal, since parties must "put their best foot forward."
The dissent disagreed that most of the action was time-barred. In its view, incurring a non-trivial expense does not on its own mean a proceeding is warranted under section 3(1)(a)(iii), and the appellants had not shown there was no genuine issue for trial on that point. The exception was the plant commissioning portion of the additional work claim: Chandos's own pleadings stated that the appellants refused compensation for that work around September and November 2017, so a proceeding was warranted by November 11, 2017 at the latest. On the contractual defence, the dissent found that GC 47.2, GC 53.2, GC 57.5, and GC 58.1 set conditions precedent to a price increase under the contract but did not expressly bar an action for damages, leaving a genuine issue for trial.
Ruling and overall outcome
The appeal by the Municipal District of Greenview No. 16 and Associated Engineering Alberta Ltd. was allowed, with one judge dissenting. Chandos's delay and additional work claims were summarily dismissed as limitations-barred. Its $311,044.91 claim for work performed during the period ending June 30, 2020 was not part of the dismissal. The decision orders no damages or other monetary amount in favour of the appellants, and it says nothing about costs.
Appellant
Respondent
Court
Court of Appeal of AlbertaCase Number
2403-0271AC; 2403-0269ACPractice Area
Construction lawAmount
Not specified/UnspecifiedWinner
AppellantTrial Start Date