• CASES

    Search by

Steelhead LNG Limited Partnership v. ARC Resources Ltd.

Executive Summary: Key Legal and Evidentiary Issues

  • Issue estoppel and abuse of process arguments based on rulings in Steelhead’s Federal Court patent action were left for trial rather than used to strike parts of Steelhead’s pleading.
     
  • Timing of the defendants’ adoption of an allegedly independent Western LNG design for the Ksi Lisims Project is a live issue for discovery and trial.
     
  • An October 1, 2020 cut-off date the defendants used to limit their document searches was rejected because it assumed the answer to a trial issue.
     
  • Proportionality widened production, but the court refused to order a forensic accounting of Steelhead’s claimed $140 million in development costs and found third-party valuations and Steelhead’s full SR&ED tax credit file irrelevant.
     
  • Written answers from three Nisga’a Nation representatives were measured against Rule 7-5, which requires proof that a non-party refused or neglected to give a responsive statement.
     
  • Bartek Kienc’s repeated lack of recollection and his refusal to answer lobbying questions justified an oral examination, while the answers from Eva Clayton and Margaret Rosling were found responsive.
     


Facts of the case

Steelhead LNG Limited Partnership and Steelhead LNG Corp. are referred to together as Steelhead, a BC company that develops liquefied natural gas (LNG) export projects. For about four years, Steelhead worked with Seven Generations Energy Ltd. (7G), the predecessor of Alberta-based natural gas producer ARC Resources Ltd. (ARC), toward a project to export LNG from BC’s coast. Around 2018, the relationship deteriorated. Steelhead sued 7G in the Supreme Court of British Columbia on July 4, 2019. It alleged that 7G used Steelhead’s confidential information and copyrighted materials to develop a competing LNG project, in breach of contractual non-disclosure and confidentiality provisions and in breach of confidence and copyright. After an amalgamation, ARC, as 7G’s successor, became the named defendant. Rockies LNG Limited Partnership and Rockies LNG GP Corp. (together, Rockies), an Alberta-based partnership of other natural gas producers, are now also defendants.

By May 1, 2020, the defendants had secured an agreement with the Nisga’a Nation to develop an LNG project on Nisga’a territory called Ksi Lisims. Western LNG, a third-party engineering company, joined in October 2020. On October 1, 2020, Rockies, Western LNG and the Nisga’a Nation executed a Cooperative Endeavours Agreement (CEA), which was amended on January 1, 2022. According to the defendants, they switched at some point to a design provided by Western LNG, and Western LNG has at all times been solely responsible for the Ksi Lisims design. Steelhead says the defendants’ competing project adversely affected its own Kwispaa LNG Project. In response, the defendants say Kwispaa failed for its own reasons before any of them reached an agreement with Western LNG or the Nisga’a Nation. Steelhead seeks damages, disgorgement of the Ksi Lisims Project’s profits, an injunction restraining further development, and a constructive trust over the project. It also asserts $140 million in development costs.

In December 2020, Steelhead LNG Limited Partnership and a related company, Steelhead LNG (ASLNG) Ltd., brought a separate patent infringement action in the Federal Court against 7G, the Rockies entities and Birchcliff Energy Ltd. A case management judge dismissed their February 2022 application for further document production and for leave to add Western LNG as a defendant. That judge found the evidence overwhelmingly showed that the Ksi Lisims design originated with Western LNG. This ruling was upheld on appeal (2022 FC 756). On July 6, 2022, the infringement action was dismissed on summary trial (2022 FC 998). Among other findings, the court held that the patented invention did not exist during the relevant period and that showing conceptual design drawings to third parties for promotional purposes was not “use” of the invention. On April 11, 2024, the Federal Court of Appeal dismissed Steelhead’s appeal (2024 FCA 67).

Three BC Supreme Court decisions followed. On October 9, 2024, the court dealt with ARC’s application to strike parts of Steelhead’s pleading and Steelhead’s request to amend it (2024 BCSC 1872). On August 18, 2026, it decided competing applications for document disclosure (2026 BCSC 1560). On October 16, 2026, it decided Steelhead’s application to examine three individuals involved in the Nisga’a Nation’s dealings with the defendants (2026 BCSC 1990).

Policy and legislative provisions at issue

ARC filed its application to strike on August 2, 2023 under Rule 9-5(1) of the Supreme Court Civil Rules, and the court decided it in 2024. ARC argued that issue estoppel and abuse of process prevented Steelhead from contradicting findings made in the Federal Court. Section 42 of the Patent Act was relevant because the Federal Court found no infringing “use” under it. That section grants a patentee the exclusive right of making, constructing and using the invention and selling it to others.

The 2026 disclosure applications turned on Rule 7-1. Under Rule 7-1(1)(a), each party must list all documents that could be used at trial to prove or disprove a material fact, and Rule 7-1(9) makes that obligation ongoing. A broader, discretionary second tier of disclosure is available under Rule 7-1(11). The test is whether the documents may help the requesting party advance its own case or damage its opponent’s case, or may fairly lead to a train of inquiry with either result. A party seeking this broader disclosure must explain why it is justified. If a demand is refused, Rule 7-1(13) lets the demanding party apply to court, and Rule 7-1(14) lets the court order a list of additional documents. Proportionality under Rule 1-3(2) is assessed against the amount involved, the importance of the issues, and the complexity of the proceeding. Schedule “A” to the October 1, 2020 CEA was also at the centre of the dispute, because it sets out Western LNG’s allegedly independent design.

The examination application was brought under Rule 7-5(1)(a). That rule allows the court to order a person who is not a party to be examined under oath if the person may have material evidence on a matter in question. Rule 7-5(3) requires affidavit evidence that the proposed witness refused or neglected to give a responsive statement, or gave conflicting statements. Steelhead bore the onus of meeting that test.

Reasoning and analysis

In the 2024 decision, ARC argued that the Federal Court had already decided key facts. These included that the Ksi Lisims design originated solely from Western LNG without reference to Steelhead’s confidential information, and that the defendants’ relationship with the Nisga’a Nation arose from a pre-existing relationship with an employee. Steelhead responded that the Federal Court issues were narrower and distinct from its breach of contract and breach of confidence claims, which fall outside that court’s statutory jurisdiction. The court found that the alleged breach of confidentiality was much broader than the design of any liquefaction facility. It extended to Steelhead’s “LNG Development Strategy,” reflecting the distinction between a project and a facility. If that information was confidential and was improperly used in pursuing Ksi Lisims, a viable claim might succeed at trial, and Steelhead should have the chance to develop it through discovery. ARC was not seeking to dismiss the action. Instead, it wanted specific allegations removed and, in effect, admissions from Steelhead. Even where the elements of estoppel are met, the court has a residual discretion to decline to apply it, and exercising that discretion calls for a nuanced inquiry into fairness. The court held that this inquiry belonged at trial, based on findings about how any confidential information was actually used. That kind of recourse was the one the Federal Court of Appeal had pointed to in its own decision.

In the August 2026 decision, the court found that Steelhead’s letter of October 22, 2025 was a valid document demand. The defendants argued the application was premature. Their point was that Steelhead had not reviewed the seventh amended list of documents, more than 100,000 pages, which they delivered on June 30, 2026, a little over a week before the hearing. Rejecting that position, the court held Steelhead was entitled to apply. Schedule “A” to the October 1, 2020 CEA did not definitively establish that an independent Western LNG design had been adopted, and some of its technical elements appeared not to be final as of that date. Steelhead was therefore entitled to drafts of Schedule “A” and any amendments to at least January 1, 2022, and to the correspondence on the design’s preparation and adoption. October 1, 2020 could not serve as a search cut-off because using it presupposed the answer to a trial question: when was the new design adopted? The court said it was not convinced that cost consequences for obstructive conduct were yet warranted. It noted, however, that on two occasions the defendants had made significant disclosures when confronted with a disclosure application, and it stated that “this is not a game of cat and mouse.”

Turning to the defendants’ eight categories, Steelhead consented to category 8 and took no position on category 2. The court described the Ksi Lisims Project as one designated to be of national importance. It found that the serious allegations of misfeasance, the complexity of the issues, and the amount in issue expanded production, but added that expanded production is not limitless. Steelhead’s existing production on its decision to pause the Kwispaa Project seemingly satisfied category 1. Under category 2, though, documents relevant to Steelhead’s efforts to advance Kwispaa after February 2019 had to be disclosed. Internal valuations of the confidential information had to be produced, and any that were privileged had to be listed and described. Third-party valuations were irrelevant, because valuation is for the court to decide with the help of qualified experts, and the request for all communications with third-party valuators was overbroad. On the $140 million in development costs, Steelhead had to give a yearly breakdown of its expenses within the more than 500 categories it had already disclosed. That breakdown had to include available details of each expense’s amount, when it was incurred, and a brief description. The court declined to order every account, invoice and payroll record for Steelhead’s entire business, agreeing with Steelhead that this would amount to a forensic accounting that was neither reasonable nor justified. Steelhead also had to disclose non-privileged documents about its investigation of rumours concerning the defendants’ business activities from 2018 to March 21, 2023, the date it commenced its claim against Rockies. The court would not decide the merits of the defendants’ limitation defence on a production application.

Two categories were refused. Communications between Steelhead and Worley and KBR were not relevant. Only the defendants and the contractors they retained would know whether those contractors were hired to leverage their knowledge of Steelhead’s information. A request for Steelhead’s entire Canada Revenue Agency SR&ED tax credit file also failed, because its contents were not relevant. Eligibility for those credits under the Income Tax Act is not the test for confidential information. The request was also overbroad, since it would capture tax assessments that are not in issue.

The October 2026 decision concerned three people. Eva Clayton is President of the Nisga’a Lisims Government Executive. Bartek Kienc is an LNG team member and regulatory and technical consultant to the Nisga’a Nation. Margaret Rosling is the Nisga’a Nation’s former external counsel. Through counsel, they had answered approximately 600 written questions: 220 to Ms. Clayton, 199 to Mr. Kienc, and 182 to Ms. Rosling. Steelhead said many answers were unresponsive or professed a lack of recollection. The respondents countered that they were strangers to the litigation and that Steelhead sought to embark on a fishing expedition. Written answers do not bar an oral examination where they are superficial or unhelpful. The court agreed with Steelhead that the action’s complexity, and the risk of inefficiency, would be amplified by multiple rounds of written questions.

Ms. Clayton’s answers were found responsive. She had explained, for example, that she did not know which factors the Nisga’a Nation considered important for LNG development because it was not her responsibility and she had no direct involvement. She had also acknowledged that briefing notes were prepared for each project agreement, but she did not indicate that she had made any inquiries about producing them. The court held that she must make those inquiries and produce the notes if available, subject to privilege, and that Steelhead could then ask further written questions about them.

Mr. Kienc was listed on approximately 800 emails disclosed by the defendants. On approximately 18 occasions he said he did not recall answers, which the court called puzzling given his extensive role. His only account of business models was a general reference to a high-level discussion with one of the defendants’ representatives. The evidence, however, showed he had met with another representative to discuss the project’s economic model. He also did not address the three years of dealings between the Nisga’a Nation and the defendants before Western LNG became involved. On lobbying materials, he refused to answer on the basis that the questions required legal interpretation. The court disagreed and held that he could speak factually about information he received as a registered lobbyist.

Ms. Rosling no longer represents the Nisga’a Nation and no longer has access to its documents. Given that, and that the events took place several years ago, the court found her responses rational.

Ruling and overall outcome

In October 2024, Steelhead succeeded against ARC’s application to strike. The court allowed Steelhead to further amend its notice of civil claim as proposed, without the additional paragraphs ARC sought to add. ARC’s application to strike or qualify parts of the pleading was dismissed. ARC was granted leave to amend its response to plead issue estoppel and abuse of process, and those questions will be decided at trial. Costs of those applications were ordered in the cause.

In August 2026, Steelhead obtained the documents sought in its application, including relief from the October 1, 2020 cut-off. The defendants were partially successful. They obtained the following:

  • Categories 1, 2 and 8.
  • Internal valuations.
  • A yearly breakdown of development costs.
  • Non-privileged investigation documents for 2018 to March 21, 2023.

Categories 6 and 7 were refused. Steelhead was awarded costs of a one-day application.

In October 2026, the court ordered an oral examination of Mr. Kienc, limited only by the Rule 7-5 requirement that questions relate to material evidence. It declined to order examinations of Ms. Clayton and Ms. Rosling, although Ms. Clayton must make inquiries about the briefing notes and produce them if available. Success on that application was divided, and each party bears its own costs.

None of the three decisions orders a specific dollar amount, so no exact monetary award can be determined.

Steelhead LNG Limited Partnership
Law Firm / Organization
Affleck Greene McMurtry LLP
Lawyer(s)

Vik Tenekjian

Law Firm / Organization
Not specified
Lawyer(s)

A.R. Wolfe

Steelhead LNG Corp.
Law Firm / Organization
Affleck Greene McMurtry LLP
Lawyer(s)

Vik Tenekjian

Law Firm / Organization
Not specified
Lawyer(s)

A.R. Wolfe

ARC Resources Ltd.
Rockies LNG Limited Partnership
Rockies LNG GP Corp.
Eva Clayton
Law Firm / Organization
Goodmans LLP
Lawyer(s)

Daniel Cappe

Bartek Kienc
Law Firm / Organization
Goodmans LLP
Lawyer(s)

Daniel Cappe

Margaret Rosling
Law Firm / Organization
Goodmans LLP
Lawyer(s)

Daniel Cappe

Supreme Court of British Columbia
S197484
Intellectual property
Not specified/Unspecified
Other