• CASES

    Search by

CNOOC Petroleum North America ULC v 801 Seventh Inc

Executive Summary: Key Legal and Evidentiary Issues

  • Validity of the tenant's 2019 lease termination depended on whether the premises were rendered unfit for occupancy under clause 17 and whether the landlord breached its covenants to comply with health and safety laws and remove hazardous substances to the extent required by law.
     
  • Alberta legislation regulating asbestos in existing buildings was considered by the court for the first time, including whether section 33 of the Occupational Health and Safety Code required removal of asbestos-containing fireproofing from the air distribution system.
     
  • Both parties alleged that the other breached the duty of good faith contractual performance between the asbestos discovery and the termination.
     
  • Expert evidence from the landlord's asbestos experts was challenged mid-trial as exceeding their qualified scope and overlapping with other landlord experts.
     
  • Post-trial disputes covered amending pleadings as of right, production of further records, and the privilege status of legal invoices in a full indemnity costs claim under clause 30.
     
  • Enforcement of a negotiated 2020 costs agreement was contested, with the tenant parties seeking to have interlocutory costs held in trust pending appeal.
     


Facts of the case

CNOOC Petroleum North America ULC, formerly Nexen, leased floors 4 through 36 of a 37-storey office tower at 801 7 Ave SW in downtown Calgary from 801 Seventh Inc. The lease was an amended and restated lease signed on December 30, 2013, with a term running to December 31, 2031. 801 Seventh Inc held title as bare trustee for six beneficial owners: OPTrust Office Inc, Centurion Holdings Ltd, Quantico Capital Corp, Westhills Development Corporation, Canadian Income Fund Group Inc and Tokay Capital Corp. On the same day, the tenant's parent, CNOOC Limited, signed an indemnity agreement covering the tenant's rent and lease obligations. The beneficial owners also signed an agreement binding their interest in the project to the landlord's lease covenants.

During a pre-renovation hazardous materials survey, the tenant's consultant, Eco Abate, reported on November 8, 2017 that the spray-applied fireproofing (SAF) in the ceiling plenum contained asbestos. The SAF coated the underside of the floor decks. According to the building's original construction specifications, it was Monokote-5, a product made with vermiculite mined near Libby, Montana. The plenum carries return air through the building's air distribution system.

More than four months after reporting the discovery to the landlord, the tenant hosted a meeting on March 14, 2018, where the landlord's representatives encountered a tenant team accompanied by lawyers. In a summary sent that evening, the tenant stated that it viewed the presence of hazardous substances as a material breach of the lease and as grounds for terminating it. Its workforce was relocated out of the building. The landlord, which was not planning to remove all the SAF in a single building-wide process during the lease term, created an asbestos management plan (AMP). On March 4, 2019, it filed an originating application seeking declarations that the premises were not unfit for occupancy and that its lease obligations to remove the asbestos-containing spray insulation could be satisfied by complying with the AMP and any future OH&S order.

A settlement meeting on May 2, 2019 failed, and the May rent went unpaid. On May 3, 2019, the tenant terminated the lease for fundamental or anticipatory breach, relying alternatively on clause 17(b). It sued the next day, and the landlord counterclaimed for wrongful termination and non-payment of rent.

Liability and damages were split into separate trial phases, with the amounts at stake described as very roughly $750 million. Judgment on liability was issued on March 14, 2025 and appealed. The appeal was argued on February 12, 2026, and no appellate decision had been released as of the court's November 20, 2026 costs ruling. Several case management rulings followed in preparation for the damages phase.

Contractual and legislative provisions at issue

Clause 17, headed "Damage or Destruction," applies if the project is "damaged or destroyed, or otherwise rendered unfit for occupancy by the Tenant." Under clause 17(b), either party may terminate only if, in the opinion of the Landlord's Architect, the project cannot be rebuilt, repaired or restored with reasonable diligence within one year. That opinion must be communicated within 30 days of the happening of the damage.

Under clause 16(j), the landlord must comply with laws "in force from time to time," including those on occupational health and safety. Clause 16(o)(ii) requires it, "to the extent required by law," to remove hazardous substances in or on the project, and clause 16(o) also contained the landlord's representation that no hazardous substances were present. Any further rules and regulations made by the landlord are, under clause 15(z), subject to prior consultation with the tenant and its agreement, failing which the matter goes to arbitration.

Section 33 of the Occupational Health and Safety Code provides that a person must not use asbestos in an air distribution system in a form or location where asbestos fibres could enter the supply or return air. Under section 31(2), all necessary steps must be taken to correct an unsafe condition. Keeping a building clear of unnecessary accumulations of asbestos, and minimizing its release into the air as far as reasonably practicable, are required by section 28.

CNOOC Limited is obliged under clause 2 of the Lease Indemnity Agreement to indemnify the landlord for losses arising from the tenant's failure to pay rent or perform its lease covenants. Clause 4 of the Beneficial Owners Agreement binds the beneficial owners' interest in the project to the landlord's covenants. A reciprocal provision in clause 30 of the lease, contemplating indemnity costs, later framed the landlord's claim for legal costs.

Reasoning and analysis

Midway through trial, in April 2023, the court ruled on the tenant's objection to seven portions of evidence from the landlord's experts, Drs. Lee and Sanchez. Both were qualified in forensic laboratory analysis and microscopy for characterizing asbestos and its potential for fibre release.

No portion was excluded for overlap under Rule 8.16(1). With close to 20 experts called, the court found that experts reached similar conclusions from their own disciplines and that the overlap was not a significant portion of their evidence. Any needless expense could be argued at the costs stage.

Overreach was treated differently, since evidence outside an expert's permitted scope is inadmissible rather than a matter of weight. The court excluded opinions that the building was "safe," that the fireproofing was in good condition and that ceiling tiles carried minimal debris. It also struck the word "non-respirable" and a reference to the particle size at which material is "potentially respirable." Two statements were allowed to stand: that W.R. Grace removed asbestos from its vermiculite, and that the building was "clean" in the narrow sense that the fireproofing was not shedding asbestos.

In the liability judgment, the court held that the clause 17 termination right can apply to a latent asbestos discovery but was not triggered here, because the tenant did not prove the premises were rendered unfit for its occupancy. Under the architect's opinion requirement, the 30-day period began when the landlord received WSP's final assessment report dated September 13, 2018. Opinions the landlord delivered on December 24, 2018 stated that the premises were not unfit. They did not address whether all the SAF could be removed or remediated within a year. That failure was a breach of the lease, but one of little consequence because the other precondition was not met.

Turning to the legislation, the court read section 33 as prohibiting the addition of asbestos to a building rather than the continued presence of existing asbestos, since it addresses a "person" and not an "employer." Full removal of the disturbed SAF was not proven to be a necessary corrective step under section 31(2).

Section 28 did impose removal obligations. Plenum debris had to be removed, and the landlord completed that work before the end of 2019. Loosely bound or dangling pieces of disturbed SAF also had to be removed where reasonably practicable. Having not failed to comply with sections 31 or 33, and being in the process of complying with other provisions at termination, the landlord was not in breach of clauses 16(j) or 16(o)(ii).

Claims for breach of quiet enjoyment, failure to operate a first-class building, denial of access and building services, and forced relocation also failed. Imposing the AMP without the tenant's agreement did breach clause 15(z), though not in a way that deprived the tenant of the whole benefit of the lease. Anticipatory breach failed as well: the evidence did not show the landlord refused to perform the lease, and it was the tenant that voluntarily brought the lease to an end.

On good faith, the landlord breached its duty of honest performance by misrepresenting that Alberta OH&S had officially approved its approach. It also evaded its clause 17 obligation to procure the architect's opinion. For its part, the tenant breached its duty of cooperation during the four months between the discovery and the March 2018 ultimatum, and misled the landlord through false representations in that period.

The evidence did not show whether the tenant acted out of concern for employee safety or to lever the discovery into a favourable lease amendment or termination. As a result, the landlord's theory that the tenant acted in bad faith throughout was not proven. A misrepresentation claim by the tenant failed because the landlord believed its no-hazardous-substances representation was true when made.

The court declined to pierce the corporate veil between the tenant and CNOOC Limited. It still held CNOOC Limited liable under the indemnity agreement, which CNOOC Limited had not denied would apply if the tenant was found liable. Liability of the beneficial owners was confined to their respective interests in the building under clause 4.

Several 2026 rulings managed the run-up to the damages phase. In February 2026, the court held that the landlord parties' December 16, 2025 Amended Response to Request for Particulars did not allow the CNOOC parties to amend their statements of defence to counterclaim as of right under Rule 3.62(3). Pleadings had closed under Rule 3.67, and Rule 3.62(3) lists specific triggering documents that do not include an amended response to particulars. Leave under Rule 3.65 was therefore required, and no costs were ordered.

A separate endorsement addressed the landlord's application for costs incurred up to entry of the order following the liability trial. Costs within clause 30 would be assessed on a full indemnity scale, using the entire amounts invoiced and paid, with no reasonableness filter. Any award would be subject to adjustment by the damages trial judge and to the outcome of the appeal.

On privilege, legal invoices remained presumptively privileged, and clause 30 did not amount to an automatic waiver. All parties were required to exchange their invoices reciprocally and were at liberty to redact privileged information. No restricted access order or publication ban was found justified.

After the CNOOC parties were permitted to amend their pleadings, they sought further and better affidavits of records, an application that failed on all four issues in August 2026. The defendants' record collection process was found appropriate, as the memo sent to custodians explained what could be relevant and material. A retention policy should have been included in that memo or sent to custodians, but its absence did not prove records were destroyed. Mr. Killi testified that he would occasionally take notes of calls with Mr. Shoraka and discard them if they held no information of an enduring nature.

Lender communications were already well covered, with 600 records produced in the Fifth Supplemental Affidavit of Records, and the pursuit of Mr. Shoraka's call logs with the lenders was characterized as a fishing expedition. So was the request for the beneficial owners' financial records, given that the defendants had formally admitted the beneficial owners had the financial capacity to pay off the mortgage, fund the building's operation and carry out any necessary asbestos removal. Communications with the landlord's insurance broker were not ordered either. Counsel had verified that the insurance did not extend to these circumstances, and the court found it unlikely that coverage would apply where a tenant stopped paying rent over asbestos-related health allegations.

Ruling and overall outcome

801 Seventh Inc was the successful party at the liability trial and in the later rulings on pleading amendments, record production and the costs agreement. The tenant was found to have unlawfully terminated the lease and unlawfully stopped paying rent, and its unjust enrichment claim for rent paid before termination was rejected. CNOOC Limited was held liable under its indemnity agreement. The tenant's limited successes on the AMP, honest performance and architect's opinion issues did not change the conclusion that the termination was unlawful.

Damages were not quantified, as they are reserved for the second phase, and the liability judgment remains under appeal. In its most recent ruling, dated November 20, 2026, the court enforced the 2020 Costs Agreement. Counsel had agreed in May 2026, after the appeal was argued, to keep it in place. It set interlocutory costs at Schedule C, Column 5 with a four-times multiple, reasonable disbursements, payable forthwith. Finding the CNOOC parties' concerns about recovery speculative, the court ordered them to pay the landlord's costs of three post-trial applications forthwith, as per the bill of costs furnished, rather than having the awards held in trust.

None of the decisions states a dollar figure for the damages or costs awarded, so no exact amount can be determined.

CNOOC Petroleum North America ULC
CNOOC Limited
Law Firm / Organization
Dentons Canada LLP
Law Firm / Organization
Burnet, Duckworth & Palmer LLP
Lawyer(s)

Jennifer Deyholos

Court of King's Bench of Alberta
1901 06261
Real estate
Not specified/Unspecified
Defendant