• CASES

    Search by

Remington Georgetown Inc. v. Tarion Warranty Corporation

Executive Summary: Key Legal and Evidentiary Issues

  • Arbitration under the Ontario New Home Warranties Plan Act is not mandatory; judicial review was a viable alternative.

  • Applicant consented to arbitration, including the use of Builder Bulletins and BAF Rules, and was not coerced into the process.

  • Court held that the arbitrator did not exceed her jurisdiction by addressing issues raised by the Applicant itself during arbitration.

  • Allegations of procedural unfairness and bias were dismissed as unsupported and improperly raised post-factum.

  • The arbitrator’s detailed 19-page decision met statutory requirements for reasoning and was upheld by the Court.

  • Applicant ordered to pay full indemnity costs of $212,000 due to meritless applications and abandonment of one after the Respondent incurred expenses.

 


 

Background and dispute origins

Remington Georgetown Inc., a residential builder, initiated legal proceedings against Tarion Warranty Corporation after an unsuccessful arbitration conducted under the Ontario New Home Warranties Plan Act. Tarion had determined that several construction defects in one of Remington’s homes constituted “chargeable conciliations,” meaning defects the builder was obligated to remedy under the Act. Remington challenged this determination in a two-day arbitration before Arbitrator Deborah Anschell, who ultimately dismissed the builder’s claim and issued a 19-page decision affirming Tarion’s findings.

Voluntariness of arbitration and legal alternatives

Remington argued that it had no choice but to enter arbitration, implying the process was mandatory and unfair. The Court clarified that arbitration under the Act is not required; the statute is silent on dispute resolution mechanisms, and arbitration is offered by Tarion as a voluntary option. Builders are free to pursue litigation or judicial review instead. The Court emphasized that Remington, an experienced builder, freely signed the arbitration agreement and was represented by counsel throughout.

Grounds for setting aside the award and court’s analysis

Remington sought to set aside the arbitral award on four grounds: excess of jurisdiction, denial of procedural fairness, arbitrator bias, and failure to provide adequate reasons. The Court reviewed each ground and found them all to be without merit:

  • Excess of jurisdiction: Remington claimed the arbitrator improperly considered defects not in the original claim. However, these issues were explicitly included in Remington’s own Request to Arbitrate. The arbitrator analyzed the documents, applied the correct warranties and guidelines, and concluded the items were properly chargeable. Her actions were within her jurisdiction under the arbitration agreement.

  • Procedural fairness: Remington alleged unfairness based on the exclusion of a knowledgeable employee, Jane Smith, from the conciliation process. The Court noted that this was due to the homeowner’s preference, which Tarion could not override. Moreover, Smith testified at the arbitration, and no objection was raised at the time. The arbitrator had addressed the issue directly and found no unfairness.

  • Bias: Remington claimed the arbitrator was biased due to her membership on Tarion’s approved roster. The Court rejected this, noting that Remington had selected her as its first choice and never raised a conflict or recusal request. No evidence of actual or perceived bias was presented. The roster’s purpose—to ensure arbitrators have relevant expertise—was found to be legitimate and not suggestive of partiality.

  • Failure to provide reasons: The arbitrator provided a 19-page written decision addressing the record, each claim, and the applicable legal standards. The Court concluded these reasons were sufficient under section 38 of the Arbitration Act and met the standard of justification, transparency, and intelligibility. The Applicant’s dissatisfaction was with the outcome, not with the adequacy of reasons.

Costs decision and implications

Following the dismissal of the set-aside application, Remington also abandoned a separate Rule 14 application challenging the validity of the BAF Rules and Builder Bulletins after Tarion had filed a full response. The Court awarded full indemnity costs of $212,000 to Tarion, referencing the broad indemnity clause in the Vendor Agreement, which required Remington to cover all costs arising from its non-performance under the Act and related instruments. The Court found that Tarion’s costs were directly tied to Remington’s unsupported challenges and that the abandonment of the second application justified a full recovery. Additionally, the Court criticized Remington for alleging bias against the arbitrator without any evidence, characterizing this tactic as improper and unnecessarily burdensome for the Respondent.

Conclusion

The Court’s rulings affirmed the integrity of the arbitration process administered under the Ontario New Home Warranties Plan Act. It rejected Remington’s procedural objections and attempts to transform the proceeding into an appeal. The Court upheld the arbitrator’s jurisdiction, fairness, and reasoning, and reinforced the enforceability of contractual cost indemnities. The decisions send a clear message that unfounded challenges and strategic litigation tactics will not be condoned and may attract substantial cost consequences.

REMINGTON GEORGETOWN INC.
Law Firm / Organization
Starkman Lawyers
TARION WARRANTY CORPORATION
Law Firm / Organization
Torys LLP
Superior Court of Justice - Ontario
CV-23-00697810-0000
Construction law
$ 212,000
Respondent